CHANGE ORDER NO.3
To contract for: Numerous misc. items, please see attached "Gilroy 6th Street Improvement Project Updated Change Order
Attachment "A", reference date 5/25/11 & Additional square footages for 2' wide brick inlays.
Don Chapin Company Contract Date: July 13th, 2010
Contractor:
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
This Change Order provides for the following:
Numerous misc. items, please see attached "Gilroy 6th Street Improvement Project Updated Change Order
Attachment" A", reference date 5/25/11.
Additional square footages for 2' wide brick inlays to make a 6' planter to match Monterey Street planter (changing
from a 4' planter).
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $112,734.17
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$1,024,474.00
$186,999.68
$1,211,473.68
$112,734.17
$299,733.85
$1,324,207.85
Percentage Initial
18.25% k\
29.26% ~
~L>v r ~~1t-J C:"l,
CONTRACTOR
B~~~
ACCEPTED BY:
C-V~
i~t0
Date
RECOMMENDED BY:
560 Crazy Horse Canyon Road
Salinas, California 93907
Phone: (831) 449-4273 Fax: (831) 449-0700
CONTRACT CHANGE ORDER
TO: Daniel Hughes, P .E. - Development Engineer C.O. #: ~
City of Gilroy
Community Development Dept.
7351 Rosanna St.
Gilroy, CA 95020
DATE: May 25, 2011
JOB NAME: Gilroy 6th St Improvements
JOB NUMBER: 210098
We hereby agree to make the change (s) specified below:
Additional work beyond scope of original contract (12/23/10 to 4/28/11)
. See attachment "A" for itemization by date, description and amount
$92,742.17
Additional sqnare footages for 2' wide brick inlays
. See contract change order attached for specific quantities and areas
$19,992.00
Note: This Change Order becomes part of and in conformance with the existing contract.
We hereby AGREE to make the change (s) specified above at this price: $ 112,734.17
Previous Contract Amount: $ 1,165,359.68
)1 Revis~tr~CtTotal: $ 1,278,093.85
BY: (-;'_ W J ,~Y--z,? ti",,----
e,ONTRACTOl}l
I
ACCEPTED - The above prices anc;V~pecifications of-this Change Order are satisfactory and are hereby
accepted. All work to be performed under the same terms and conditions as specified in original contract
I agreement unless otherwise stipulated.
DATE:...c;J5.(~ J/
DATE:
BY:
OWNER
GILROY 6th Street Improvement Project
Updated Change Order Attachment "A", reference date 5/25/11
EWR Ref. # Date Description Amount & Date Requested
April 5. 2011 May 25, 2011
50 04/28/11 Off haul concrete and spoils $ 1,887.04
49 04/21/11 Remove 9' of curb and gutter @ Copy/Fax driveway due to utility conflict $ 414.58
48 04/21/11 Install mortar B-9 boxes @ Harvest Time restaurant alley & Copy/Fax Bldg $ 179.90
47 04/21/11 Materials for driveway drains @ Harvest Tim & Copy/Fax bldg driveways $ 425.62
46 04/19/11 Install curb drains from alley @ Harvest Time & Copy/Fax driveway $ 1,609.35
45 04/18/11 Sign post material $ 322.70
44 04/08/11 Remove concrete road section & replace with AC $ 3,954.83
43 04/14/11 Sawcut cracked concrete road for AC conform on 6th St westside southside $ 1,236.76
42 04/14/11 Remove concrete conforms @ Harvest Time alley and Coy/Fax bldg $ 1,546.66
41 04/12/11 Sawcut concrete driveway conforms @ Harvest Time & Copy/Fax bldg $ 862.69
40 04/11/11 Core drill curb for roof drain $ 1,667.41
39 04/04/11 Sawcut concrete & remove, alley D/VV - remove sign & foundation @ Halls Bldg $ 1,407.64
38 03/30/11 Sawcut & chip concrete off edge of bldg foundatio Old Post Office $ 1,396.77
37 02/24/11 Excavate to install sleeve, include hot tap $ 4,894.23
36 01/19/11 See previous change order request dated 4/5/11 $ 490.14
35 03/22/11 Install irrigation sleeve in front of Harvest Time Rest on 6th Street $ 6,836.74
34 03/21/11 Raise water valve on 6th Street and Alley $ 1,333.41
33 03/17/11 Place fabric over subgrade $ 773.34
32 03/16/11 Stand-by for unmarked water service repair $ 438.76
31 03/15/11 Additional sawcuts at 6t Street $ 1,313.39
30 03/10/11 Demo, remove and replace existing concrete roadway with 3/4" AC $ 13,044.75
29 03/08/11 Sawcut asphalt concrete for conform work $ 2,961.14
28 03/07/11 6" water tie-in to 12" water main, remove existing 6" valve off of tee and place cap $ 4,603.68
27 03/02/11 Handout new water shut off notices with new date for 6th and Gourmet Alley $ 201.16
26 03/01/11 Pothole, install new customer from meter box to POC behind Econo Furniture $ 3,511.81
25 02/28/11 Pothole existing lines on 6th & Railrod , 4 locations. $ 3,647.93
Connect new 1" PVC line to existin copper line
24 03/03/11 Relocate exisiting water meter to water box @ OW approach $ 1,711.20
Potholed, installed new customer from new meter box to POC in parking lot
23 03/01/11 behind Econo Furniture $ 3,611.35
Saw cut asphalt and concrete for hot tap in alley & water lines @ Railroad Street
22 02/24/11 & 6th $ 2,222.99
21 02/23/11 Potholed water lines on 6th Street and Railroad and behind Econo Furniture $ 4,152.56
20 02/22/11 Potholed water lines behind Halls Building $ 838.43
19 02/10/11 Materials Only $ 1,133.07
18 02/15/11 Standby for two unmarked 1" water services $ 1 ,899.53
17 01/31/11 Remove additional street surface & repace to remove trenchline (Difference) $ 1,974.65
16 01/27/11 Sawcut concrete trench settlement In roadway $ 1,184.14
15 01/26/11 Remove asphalt for conform behind S.W. & furniture store parking lot $ 931.10
14 01/25/11 Conform sawcut at Econo Funriture $ 3,008.49
13 01/19/11 Sawcut asphalt conform at furniture store. Sawcut concrete road on 6th. $ 1,009.30
12 City of Gilroy CO #2 n/a
11 01/11/11 Demo, remove, dispose of 190 sf of sidewalk on East sidde of railroadtracks $ 1,649.91
10 01/06/11 Install curb at Econo Furniture $ 2,049.55
9 01/05/11 Install curb next to Econo Furniture $ 2,398.69
8 Charge to Alpha & Omega (Not City Expense) n/a
7 12/23/10 Set and pour driveway at roll up door $ 2,004.78
$ 61,833.74 $ 30,908.43
1'0
" \~T :Qt~l :Q~tstatlding:'
; ::" (- -' ~-.:_:~:
':~:;:;'
, .'.' ..' ','" :.,'<:$ ",<:, '
'....,. ""'c
.', =,.....,
;9,2f(4~:1~ :\
5MI Crazy Horse Canyon Road
Salinas, California ~l3907
Phone: (831) 449-4273 Fax: (831) 449-0700
CONTRACT CHANGE ORDER
TO: Daniel Hughes, P.E. - Development Engineer
C.O.#:
City of Gilroy
Community Development Dept.
7351 Rosanna St.
Gilroy, CA 95020
! DATE: May 25,2011
I
JOB NAME: Gilroy 6th St Improvements
JOB NUMBER: 210098
We hereby agree to make the change (s) specified below:
Additional square footages for 2' wide brick inlays;
SE 150 Ifx 2 = 300 sf
SW 95 Ifx 2 = 190 sf
NW 1691fx 2 = 338 sf
NE 1741fx 2 = 348 sf
TOTAL 1176 sf
Deduct 1,176 SF @ $8.00 per SF = ($9,408.00)
Add 1,176 SF @ $25.00 per SF = $29,400.00
We hereby AGREE to make the change (s) specified above at this price: S 19,992.00
Previous Contract Amount: $
DATE:
Revised Contract Total: $
ACCEPTED - The above prices and spe~ifications of this Change Order are satisfactory and are hereby
accepted. All work to be perfonned under the same terms and conditions as specified in original contract I
agreement unless otherwise stipulated.
DATE:
BY:
OWNER