HomeMy WebLinkAboutGabel Paving, Inc. - Camino Arroyo Bridge Project No. 07-CDD-141 - Change Order No. 1 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0450; Fax (408) 846-0429 CHANGE ORDER NO.1 To contract for: Camino Arroyo Bridge Project, Phase I Project~o. 07~I>I>-I41 Contractor: Galeb Paving, mc. Contract I>ate: 7/16/2007 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. I>escription of Work This change order provides for the following: - Additional surveying at various locations per attached extra work invoices dated October 31,2007. - Removal and replacement of35 feet of curb & gutter at northwest corner of Rogers Lane and Sixth Street per attached extra work invoice dated October 31, 2007. - Modify Manhole C per revised Sheet 32Rl per attached extra work invoice dated ~ovember 12,2007. -Relocate water line at southeast corner of Alexander Street and Sixth Street per attached invoice dated ~ovember 21,2007. -mstall drain box at northwest corner of Chestnut Street and Sixth Street per attached invoice dated ~ovember 5, 2007. All requirements of the original Contract I>ocuments shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. By: Original Contract Price Previous Change Orders Total to I>ate This Change Order Total Change Orders to I>ate Revised Contract Price Cost Percentage Initial $2,438,986.62 $0.00 0.00010 $2,438,986.62 $23,701.88 $23,701.88 0.97% $2,462,688.50 I (We) agree to make the above change subject to the terms of this Change Order for the ~T mCREASE of $23,701.88 c;.-,1-- LV D P A-V"'! G-:- I q< c. I'- I>ate: IIIZ7/07 ACCEPTEI> BY: .... '" " <' ;"r- RECEIVED OCT 3 1 2007 ENGINEERING GALEB PAVING, INC. General Engineering Contractors Since 1975 State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 10/31/2007 Hand Delivered at Site MeetinQ City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE It PROJECT #07-CDD-141 EXTRA WORK Date SubContractor Work Units/Hours De,cription/Equipment Rate/hr. Amount 10-1-07 Ruggeri Jensen Azar & Assoc. Extra Staking, Site Grade $ 4,800.50 (see attached tags) Extra Staking SUB-TOTAL: 5% P. & 0.: SUB-TOTAL: 1% BOND: TOTAL: $ 4,800.50 $ 240.03 $ 5,040.53 $ 50.41 $ 5,090.93 Sincerely, c~ ~ObOdan Galeb . . Page 1 of 5 . -.--------. GALEB PAVING, INC. General Engineering Contractors Since 1975 RECEIVED OCT 3 1 Z007 ENGINEERING State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 10/31/2007 Hand Delivered at Site MeetinQ City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK Date SubContractor Work Units/Hours pescription/Eql.lipment Rate/hr, Amount 10-22-07 Ruggeri Jensen Azar & Assoc. Extra Staking, Site Grade $ 7,620.50 (see attached tags) Extra Staking SUB-TOTAL: 5% P. & 0.: SUB-TOTAL: 1% BOND: TOTAL: $ 7,620.50 $ 381.03 $ 8,001.53 $ 80.02 $ 8,081.54 Sincerely, ----~ ~1~Odan Gal?~ - Page 1 of 6 GALEB PAVING, INC. General Engineering Contractors Since 1975 State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 RECEIVED OCT 3 1 2.007 ENGINEERING 10-31-07 Hand Delivered at Site Meetina City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK Date SubContractor Work Units/Hours De,criptlon/Equipment Rate/hr. Amount 10-11-07 C. Aparicio Cement Contractor, Inc. Remove/Replace 35' Curb / Gutter @ $ 2,150.00 (see attached breakdown) H.C.R. on Northwest corner of Rodgers and 6th Street SUB-TOTAL: 5% P. &0.: 8UB-TOTAL: 1% BOND: TOTAL: $ 2,150.00 $ 107.50 $ 2,257.50 $ 22.58 $ 2,280.08 Sincerely, L _:.~ ~~bOdan Gal?~"""-- Page 1 of 2 RECE\VED i'!O'l 1 , 7,007 c~~G\NEER\NG 1._1' GALEB PAVING, INC. General Engineering Contractors Since 1975 State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 11/12/2007 Hand Delivered City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE It PROJECT #07-CDD-141 EXTRA WORK PROPOSAL Date SubContractor Work Units/Hours Description/Equipment Rate/hr. Amount 11/8/07 George D. Garcia, Inc. Extra cost for manhole C per Revision $ 4,522.00 (see attached breakdown) 32R1 - This in addition to contract item SUB-TOTAL: 5% P. & 0.: SUB-TOTAL: 1% BOND: TOTAL: $ 4,522.00 $ 226.10 $ 4,748.10 $ 47.48 $ 4,795.58 Sincerely, //~ ~#- Slobodan Galeb ,/ ~ ' I Page 1 of 2 GALEB PAVING, INC. General Engineering Contractors Since 1975 RECEIVED >~ov 2 1 /:007 ':::l\IGiNEEHIN(3 State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 11/21/2007 Hand Delivered at Site MeetinQ City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK PROPOSAL Dear Charlie, Per our agreement, the following is a detailed cost breakdown for relocating the water line at the S/E corner of 6th & Alexander. Date SubContractor Work Units/Hours Des4;t'lptiot'l/Equipment Rate/hr. Amount , 11/19/07 George D. Garcia, Inc. Lower water lines that are up in $ 1,748.00 (See attached breakdown) grade at S/E corner of 6th & Alexander SUB-TOTAL: 5% P. & 0.: SUB-TOTAL: 1% BOND: TOTAL: $ 1,748.00 $ 87.40 $ 1,835.40 $ 18.35 $ 1,853.75 Sincerely, ( ,~~...4.. '- -- ////'{,~(/ Slobodan Gale!:)/ / Page 1 of 2 11/135/213137 17:17 41382534753 GALES PAVING INC PAGE 131/132 --' GALES PAVING, INC. General Engineering Contractors Since 1915 State Ucense No. 325912 12340 Saratoga - Sunnyvale Rd., SaratQga, CA 95070 TelephOne: (408) 253-4747 Facsimile: (408) 253-4753 <") . ",~.. .' "\~' ,.-, i'~ ; C'-'" ""''', ,." L. ( f.' I ". ;1"'1 ; .l._ .,1._ ) I__.J 5-Nov-07, City of Gilroy Attention: Charli~ Kreuger 7351 Rosanna Street Gilroy, Ca 95020 NOV Ii 2001 ENGINEERING JOB SITE: CAMINO ARROYO BRIDGE PHASE 1, PROJECT #t07~CDP~141 EXTRA WORK Dear Charlie, The following is a detailed cost breakdown to cleanup, restore and recompact CL II AB grade at the NIW corner of 6th Street & Chestnut. 6508 Tractor Laborer Dump TnJck Grade Cchecker BW 120 AD Roll Water Truck CL II AB Galeb Pavma, Inc. Work: $ G96.90 ll/lf1.OO7 Work to be performed by George P. $ 1,122.00 Garcia. InC. (see attached QUota) to add 8r:lr:ll(. .25 L.F. 6" SOR35 RVe at NJW com., of 6th Street & Chestnut. Add 1 each V1 box wIth grate SUB-TOTAL: 15% P." 0.: 608.00 90.90 Sincerely, SUB~TOTAL: 6% P. .0.: George D. Garcia, lac. Worki SUB-TOTAL: 1 % BOND: TOTAL LUMP SUM PRICE. $ 1,122.00 $ 56.10 $ 1.178.10 $ 1,875.00 $ 18.75 . $ - 1,893.1lo ..-'~-~&r I b/_ .. __ ~ .. /!f,L- Via Facsimile: 408-846-0429 Paae 1 of 2 >$ /.600 , A1/'tEe4 >J li/zllo7 qK Torno Galeb