HomeMy WebLinkAboutGabel Paving, Inc. - Camino Arroyo Bridge Project No. 07-CDD-141 - Change Order No. 2
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846-0450; Fax (408) 846-0429
CHANGE ORDER NO.2
To contract for: Camino Arroyo Bridge Project, Phase I
Project No. 07-CDD-141
Ga]eb Paving, Inc.
Contract Date:
7/16/2007
Contractor:
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
-Additional grading at sidewalk areas on north and south sides of Sixth Street.
-Remove concrete slab on south side of Sixth Street east of Maple Street on 11/21/04 and 11/28/07.
-Restock ductile iron pipe eliminated from project per Letter No. 21.
-Work around four utility poles shown on plans to be removed by others.
-Construct, install, remove and dispose of two gateway pilaster mockups per Letter No. 46.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$2,438,986.62
$23,701.88
$2,462,688.50
$]8,0]7.71
$41,719.59
$2,480,706.21
Percentage Initial
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $18,017.71
0.97%
)- ~U
CONTRACTOR
By: &-4?C ~ f"14r/~ate:
1.71%
3/ s { o~
RECOMMENDED BY:
ACCEPTED BY:
GALES PAVING, INC.
General Engineering Contractors Since 1975
RECEIVED
NO\] 3 0 2007
ENGINEERING
State License No. 325912
12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070
Telephone: (408) 253-4747
Facsimile: (408) 253-4753
11/30/07
Hand Delivered
City of Gilroy
Attention: Charlie Kreuger
7351 Rosanna Street
Gilroy, Ca 95020
JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141
EXTRA WORK PROPOSAL
Dear Charliet
The following is a detailed cost breakdown for additional grading required at the
sidewalk areas on the North side of 6th Street.
$ 1,520.00
16 $ 800.00
16 $ 1,600.00
8 $ 640.00
SUB-TOTAL: $ 4,560.00
15% P. & 0.: $ 684.00
SUB-TOTAL: $ 5,244.00
1% BOND: $ 52.44
TOTAL: $ 5,296.44
Sincerely,
j~*
Slobodan GaleY Y (/
01/10/2008 15:35
4082534753
GALEE PAVING INC
PAGE 01/01
GALES PAVING, INC.
General Engineering Contractors Since 1975
State Ucansa No. 325912
12340 Saratoga - Sunnyvale Rd., Saratoga. CA 95070
Telephone: (408) 263-4747
Facsimile: (408) 253-4753
1-10-08
City of Clll'oy
Attention: Charlie Kreu:er
7351 Rosanna Street
Gilroy, Ca 95020
.JOB SITE: cAMiNo ARROYO BRIDGE PHASE It PROJECT #07-CDD-141
EXTRA WORK PROPOSAL
Dear Charlie,
The following is a detailed cost breakdown for additional grading required at the
sidewalk areas on the South side of 6th Street.
''''{lI'r-I''~m~'Y~'I(I~''.'"'~ffill'l'I''III'I''II~{b''''"' l'j;C'..lll!TmT~~'~I"'~.II""'-I"'r""""JII'"'T~rr;z;"'''.''~lli~~Iill?r''1'.'~'''1
.Jt~,t.l..\ L hI . ,1 w). J ) t::Uitrl ;-....."illr ~ y\}, ,r' , !,\;n .:; ,.;' f'~H)/! 1,;,r,t~ 74.llL~irl(~((f ~",~,J,},JUf 1I : '~, ;.\ \-,~.'~, I' '" )1 H~~rr; l , r"HII',},n
L $ 650B Tractor $ 95.00 $ 760.00
8 Uiboror $ 50.00 S 400.00
8 Roller $ 100.00 $ 800.00
4 Water Truck $ &0.00 $ 320.00
SUB-TOTAl.:
15%P.&O.:
SUB.TOT.hJ.1
1% BOND:
TOTAL:
S 2,280.00.
S 342.00
S 2,622.00
$ ~6..22
$ ".64A.22
Sincerely,
---~ J
- ,..,- 1"- c:4.,
tf
Torno Galeb
Vik ~ c0i~II.e I (-4i18') g l{-& - otf J- q
,/
GALE'B PAVING, INC.
General Engineering Contractors Since 1975
State License No. 325912
12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070
Telephone: (408) 253-4747
Facsimile: (408) 253-4753
City of Gilroy
Attention: Charlie Kreuger
7351 Rosanna Street
GilroYt Ca 95020
JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141
EXTRA WORK
RECEIVED
NOV 3 0 Z007
ENGINEERING
11/30/07
Hand Delivered
Dear Charlie,
The following is a cost breakdown to perform concrete removal underneath the
structural pavement as identified on 11/21/07.
225 Excavator w/hydrohammer attachment
CAT 4200 Backhoe
Laborer
10 Wheeler Truck
End Dump Truck
973 Loader with 4:1 bucket
Dump Fee (NO CHARGE)
SUB-TOTAL:
15% P. & 0.:
SUB-TOTAL:
1% BOND:
TOTAL:
$
$
$
$
$
$
$
$ 1,870.00
$ 280.50
$ 2,150.50
$ 21.51
$ 2,172.01
Sincerely,
/' ~-
Slobodan Galeb ~
: : . ~ .' l' .
Page 1 of 2
/
GALES PAVING, INC.
General Engineering Contractors Since 1975
RECEIVED
NOV 3 0 2007
ENGINEERING
State License No. 325912
12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070
Telephone: (408) 253-4747
Facsimile: (408) 253-4753
11/30/07
Hand Delivered
City of Gilroy
Attention: Charlie Kreuger
7351 Rosanna Street
GilroYt Ca 95020
JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141
EXTRA WORK
Dear Charlie,
The following is a cost breakdown to perform concrete removal underneath the
structural pavement as identified on 11/28/07.
11/28/07 Remove .additional concrete underneath
existing structural pavement section @
bus stop between Rogers & Maple.
2
2
2
2
3
1
1
1
225 Excavator w/hydrohammer
Dump Truck (10 Wheeler)
6508 Tractor
Laborer
End Dump Truck
973 Track Loader with 4:1 bucket
Dump Fee (NO CHARGE)
Foreman (NO CHARGE)
$ 250.00 $
$ 80.00 $
$ 95.00 $
$ 50.00 $
$ 90.00 $
$ 195.00 $
$ $
$ $
$
$
$
$
$
SUB-TOTAL:
15% P. & 0.:
SUB-TOTAL:
1% BOND:
TOTAL:
500.00
160.00
190.00
100.00
270.00
195.00
1,415.00
212.25
1,627.25
16.27
1,643.52
Sincerely,
Page 1 of 2
/..
GALEB PAVING, INC.
General Engineering Contractors Since 1975
State License No. 325912
1 2340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070
Telephone: (408) 253-4747
Facsimile: (408) 253-4753
RECEIVED
DEe 1 1 2007
ENGINEERING
12/07/07
Hand Delivered
City of Gilroy
Attention: Charlie Kreuger
7351 Rosanna Street
Gilroy, Ca 95020
JOB SITE: CAMINO ARROYO BRIDGE PHASE It PROJECT #07-CDD-141
EXTRA WORK
11/27/07 George D. Garica, Inc.
(see attached breakdown)
108 L.F. 12" D.I.P. Restock, crew to
load, and truck to return pipe
SUB-TOTAL:
5%P.&O.:
SUB-TOTAL:
1% BOND:
TOTAL:
$ 1,195.92
$ 59.80
$ 1,255.72
$ 12.56
$ 1,268.27
Sincerely,
~ ~
.Slobodan Gale
"/ ~'-....;'
Page 1 of 3
Bl/22/2BB8 13:24
4B82534753
GALEE PAVING INC
"
GALEB PAVING, INC.
General Engineering Contractors Since 1975
state Ucense No. 32~912
12340 Saratoga ~ Sunnyvale Rd., Saratoga, CA 05070
Telephone: (408) 253-4747
Facsimile; (408) 253-4753
City of Gilroy
Attention: Charlie Kreuger
7351 Rosanna Street
GUroy, Ca 95020
JOB SITE~ CAMINO ARROYO BRIDGE PHASE It PROJEC'r '07-CDD-141
EXTRA WORK
1-17-08
PAGE BlfBl
. :~
Dear Charlie,
The following is a detailed. cost breakdown to work around (4) utility poles shown
on drawing 43 of 65 to be removed by others.
m -".ffu~",'i1t~I' nl' 'r-vr '.1' 1"""""'f;"l"tf'--~r'..m':~cl~':''''.!M'WI';1 '''r~'~ffi~miJj. ~1"" 1 "1.1~',j~!m' f~': ,Ij 'I '11 "'T ::l!hlll
:; a:)i:~r.zJ;f Ii ttP~ In: rl,)~l ~ ' :.tJ.~!J;JU~t ~~,.l 1~' ~1&;~j T'ltl i~d, ~AJd,t.:'l.1(' J~ ~~ hlb1 '1;~1fiJl[f~~ i ~/l Lli1)q,\~hl\~~t(.
Galeb paving. Inc. 2 140H Motorgrader $ 170.00 $ 340.00
2 816 Cornpaetor $ 165.00 S 330.00
2 325 Excavator $ 165.00 $ 330.00
4 Laborer (jumping Jack) $ 50.00 $ 200.00
4 Laborer (shoveling) $ 50.00 $ 200.00
4 6508 Tractor $ 95.00 $ 380,00
4 BW120AD $ 9~.OO $ 380.00
1 1-DayJumplng Jack $ 125.00 $ 125.00
04- Foremsn/Plcl(up $ 81.00 S 324.00
SUB-TOTAL!
15% P. & 0.:
SlJB-'1'O'1'ALl
1% 80ND:
TOTAL:
$ 2,609.00
$ 391.35
$ 3,00D.35
$ 30.00
S . .. 3.0.~.35
Sincerely,
Via Facsimile:
(40S) 848-0429
,-- <j---:::: "r~
Torno Galeb
, .
..;~. 0, ,~~
,:,:"",,'-~'":,".
,
/
GALEB PAVING, INC.
General Engineering Contractors Since 1975
State License No. 325912
12340 Sa~atoga - Sunnyvale Rd., Saratoga, CA 95070
Telephone: (408) 253-4747
Facsimile: (408) 253-4753
City of Gilroy
Attention: Charlie Kreuger
7351 Rosanna Street
Gilroy, Ca 95020
RECEIVED
JAN 3 0 2008
ENGINEERING
1/28/08
HAND DELIVERED
JOB SITE: CAMINO ARROYO BRIDGE PHASE It PROJECT t#07-CDD-141
EXTRA WORK
12/28/08 George D. Garica, Inc.
(see attached breakdown)
Build & Install Temp Wood Pilaster
at Railroad
(George D. Garcia, Inc.
(see attached breakdown)
Remove Temp Wood Pilaster at
Railroad & Take to Dump
$
99.00
SUB-TOTAL:
5% P. & 0.:
SUB-TOTAL:
1% BOND:
TOTAL:
$ 1,847.15
$ 92.36
$ 1,939.51
$ 19.40
$ 1,958.90
Sincerely,
f ~-
Slobodan G~'p'" V-
.:f::
Page 1 of3