HomeMy WebLinkAboutGabel Paving, Inc. - Camino Arroyo Bridge Project No. 07-CDD-141 - Change Order No. 4 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0451; Fax (408) 846-0429 CHANGE ORDER NO.4 To contract for: Camino Arroyo Bridge Project, Phase I Project No. 07-CDD-141 Contractor: Galeb Paving, Inc. Contract Date: 7/16/2007 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work This Change Order provides for the following: Construct additional drainage inlet on north side of Sixth Street west of Maple Street. Modify catch basin at northwest comer of Sixth Street and Railroad Street. Revise forms for raised curb at northeast comer of Sixth Street and Railroad Street. Remove and replace sidewalk at southwest comer of Sixth Street and Chestnut Street. Construct temporary AC walkways at northwest and southwest comers of Sixth Street and Railroad Street. Overhead compensation due to deleted contract bid items 9, 10, 75, 76 and 77. Remove buried concrete in conflict with conduit boring operation. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. f-- Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost $2,438,986.62 $60,430.60 $2,499,417.22 $16,979.74 $77,410.34 $2,516,396.96 Percentage Initial 2.48% ~ 3.17%~ I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $16,979.74 CONTRACTOR By: :;; {ob()t{an ~I.e Date: / 0/1'1/0 t ACCEPTED BY: Engineer pmj~~=~ IO/I'/or . RECOMMENDED BY: Date / GALEB PAVING, INC. General Engineering Contractors Since 1975 RECEIVED OCT 3 1 2007 ENGINEERING State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 10-31-07 Hand Delivered at Site MeetinQ City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK C. Aparicio Cement Contractor, Inc. (see attached breakdown) Add extra City St. Flat Grate Inlet on the North side of Sixth Street SUB-TOTAL: 5% P. & 0.: SUB-TOTAL: 1% BOND: TOTAL: $ 3,208.00 $ 3,208.00 $ 160.40 $ 3,368.40 $ 33.68 $ 3,402.08 Sincerely, A~ Slobodan Gal Page 1 of 2 / GALEB PAVING, INC. General Engineering Contractors Since 1975 RECEIVED OCT 3 1 2007 ENGINEERING State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 10-31-07 Hand Delivered at Site MeetinQ City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK c. Aparicio Cement Contractor, Inc. (see attached breakdown) ",Unit$1HoufS,; ... . ~ctiPt;q~Ciuipment. ,. Cap off old existing catch basin top & place a new pipe (supplied by others) from new catch basin to existing catch basin on the Northwest corner of 6th 51. & Railroad SI. - 9/13 -18/2007 SUB-TOTAL: 5%P.&O.: SUB-TOTAL: 1 % BOND: TOTAL: Amount 3,191.47 $ 3,191.47 $ 159.57 $ 3,351.04 $ 33.51 $ 3,384.55 Sincerely, I'- ~ Slobodan Gal~ Page 1 of 2 / i i .--- GALEB PAVING, INC. General Engineering Contractors Since 1975 State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 Facsimile: (408) 253-4753 1-16-08 City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy t Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK 12-19-07 C. Aparicio Cement (see attached exta) "l''',,: w"",,,,'_ ...~ Reset form for the Raised Curb on the Northeast corner of 6th Sl & Railroad Per Charlie Krueger Remove/replace Sidewalk on the Southwest corner ofjth& Chestnut SUB-TOTAL: 5% P. & 0.: SUB-TOTAL: 1% BOND: TOTAL: $ 944.48 $ 2,136.31 $ 106.82. $ 2,243.13 $ 22.43 $ 2,265.56 Sincerely, 1- ~ Slobodan Ga';;fPTP'Y , J n .rrA CC;?"VV/.; Ie: 'v l'vI --r{,tl 0og) 254lt?-o42Q Page 1 of 3 02/14/2008 15:33 4082534753 GALEB PAVING INC PAGE 01/05 GALES PAVING, INC. General Engineering Contractors Since 1975 State LIcense No. 325912 12340 Saratoga - Sunnyvale Ad., Saratoga, CA 95070 Telephone; (408) 253-4747 Fac9imlh~: (408) 253-4753 14-Feb-08 City of Gilroy Attention: Charlie Kreuger 73S 1 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE I, PROJECT #07-CDD-141 EXTRA WORK 2/12f08 Galeb Paving, Inc. - Temporary Paving 4 4 2 120 AD Roller $ 650 Ferman $ Foreman & Pickup $ SUB-TOTAL: lS% P. & 0.: bP W 2463 $ 22.34 $ B1.00 $ $ $ $ 98.52 89.36 182.00 349,88 52.48 40 36 Gale avine, Inc. ork: 2. 1/12/08 Work performed by George O. Garcia, Inc. Raise base rock. from 4" for $ 3,429.21 l(se8 attached Quota} concrete to 2" for temp A.C. walk. Place 2" A.C. '1/1'1/08 work pertormed by George D. Garcia, lOCi. Remove 2 small tree & haul to $ 131.56 I/sae attached Cnlote) dum" 3M! corner Chestnut & 6th Stral1lt Sincerely, SUB.TOTAL: 5%P. &0.: George D. Garejat Inc. Work: SUB"TOTAL: 1"10 BOND: TOTAL EXTRA WORK: $ 3,560.77 $ 178.04 $ 3,738.81 $ 4,141.17 $ 41.41 $ 4,182.58 ---e r J ~ 1<<----. Torno Galeb Via Facsimile: 408.846-0429 Paae 1 of6 /" GALEB PAVING, INC. General Engineering Contractors Since 1975 State License No. 325912 12340 Saratoga - Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253'-4747 Facsimile: (408) 253-4753 RECEIVED MAR 5 2008 I=NGINEERING 3-5-08 Hand Delivered @ MeetinQ City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy, Ca 95020 JOB SITE: CAMINO ARROYO BRIDGE PHASE It PROJECT #07-CDD-141 EXTRA WORK 2-7-08 Chrisp Company (see attached breakdown) Overhead Compensation Due to Deleted Contract Items #75, #76, #77, #9, & #10 $ 1,051.31 SUB-TOTAL: 5%P.&0.: SUB-TOTAL: 1% BOND: TOTAL: $ 1,051.31 $ 52.57 $ 1,103.88 $ 11.04 $ 1,114.91 Sincerely, Il # Slobodan Gale. Page 1 of2 07/11/2008 11:25 4082534753 GALEB PAVING INC PAGE 01/04 (.~--""" GALEB PAVING, INC. Gen~ral Engineering Contractors Since 1975 $tate UC8flae No. 325912 12340 Saratnga . Sunnyvale Rd., Saratoga, CA 95070 Telephone: (408) 253-4747 facsimile: (408) 253.4TSS 718/08 City of Gilroy Attention: Charlie Kreuger 7351 Rosanna Street Gilroy~ Ca 95020 JOB SITE: CAM~NO ARROYO BRIDGE PRASE It PROJECT #07-CDD"141 EXTRA WORK 'a"-".""f"-"i"111~!,j'(J'lWllJ!~. '~".~ (~"'''~.:;r;'''''''''\'".''''l'r~ ij'il~'~ll '1' r .. ~'I r,,,'(,, ""'jI",!!' J~'1Jmlll1!i"::"""' , --. T'" 'ffi~I]l'-:,"jIT'jIT-r;."" 11'.I~~ill"~; I" >""'W"~t"'I. : rnl'~ ~,:Jif~! .i.hT~l [j .?)'jit;~:;~'t\,,":dl~ ~jrl.~tl~;\flTPf.~~,' tIt 1 t 1f. ~~:r,J '~l:l ~1~~L",\".J'';.'~1 '1. !.t'~ r ,it:{.1J 'r),.1 ")"1 ; ii~t7'h:~j-ll.)\; jf~' ~;,,;' ~~tlr.t\or~;&r 1CV10/07 Signal Ell!!ctti<:, IrI<:. Unforseen work. - R,emQVe QOncrete $ 2,,480.02 1 (S88 attached breakdown) in way of bor8 In two loe.atlons at 6th Street & Railway SUB-TOTAL: 5%P.& 0,: SUB-'l'O'l'U: 1 % BONO: '1'O'J'Al.: . $ 2,480,02 $ 124.00 $ 2,604.02 $ 28.04 $ 2,830.08 Sincerely, /:OOdan Ga~ Via Facsimile: (408) 846-0429 Page 1 of 4