HomeMy WebLinkAboutGranite Construction - Santa Teresa Blvd. Widening Project - Change Order No. 02
035
qcitp of ~ilrop
Planning Division
Engineering Division
Building, Life & Environmental Safety Division
Housing & Community Development
COMMUNITY DEVELOPMENT DEPARTMENT
7351 Rosanna Street, Gilroy, CA 95020
(408) 846-0440 FAX: (408) 846-0429
(408) 846-0450 FAX: (408) 846-0429
(408) 846-0430 FAX: (408) 846-0429
(408) 846-0290 FAX: (408) 846-0429
CHANGE ORDER NO.2
To contract for:
Santa Teresa Boulevard Widening Project
Project No. 04-CDD-128
Contractor:
Granite Construction Company
Contract Date: 5/17/04
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
the City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be
returned to him as his authority to proceed with the work.
Description ofW ork:
Construct alternate pavement section consisting of 6" AC over 6" Class 2 AB over 15" lime-treated
subgrade (4% Quicklime Plus) per attached letter dated July 23,2004. Work shall be performed in
accordance with Section 24 of the Caltrans Standard Specifications. Section 24-1.04 and 24-1.09 are
modified as follows:
24-1.04 PREPARING MATERIAL
Unless otherwise ordered or approved by the Engineer, the material to be stabilized shall
be placed to the lines, grades and dimensions shown on the plans before lime is added.
The surface of the material to be stabilized shall not vary more than 25 mm (0.08-foot)
above or below the grade established by the Engineer, before lime is added.
24-1.09 CURING
Curing by water will be permitted. Curing period shall be 4 days, with 3 daily
applications of water.
The contract bid items are adjusted as follows:
Unit Orig. Revised
Item Description Unit Price Quantity Ouantity Savings
21 Roadway Excavation (F) CY $3.00 39,000 14,850 . $72,450
52 Asphalt Concrete Ton $53.00 23,246 20,862 $126,352
53 Aggregate Base (F) Ton $6.00 66,400 32,171 $205,374
54 Filter Fabric SY $1. 00 60,000 0 $60.000
$464,176
Page 1 of2
"First In Service to the Community"
The following additional costs are included in this change:
Description
Unit
Amount
Lime Treatment
Contractor's Share of Savings
LS
LS
$ 368,125
$2 L 051
$389,176
Net Decrease = $75,000
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET DECREASE of $75,000.
6~\1t ~~ilo"'; tor4'~
By' It ClJr //
~ Date: 11/l7Ia!
Original Contract Price:
$7,448,458.00
Previous Change Orders:
18,280.00
TOTAL TO DATE:
$7,466,738.00
(75,000.00)
lIDs Change Order:
Revised Contract Price:
$7,391,738.00
".--..... f)
(~:...<<. ..')~\~..9- )
ACCEPTED' ,..:::::......".:'"':..:~--."",........ ....... --..::;;;r
( c;i~ A'.. ''''~''''
Page 2 of2
Charlie Krueger
Ghiradelli Associates
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
RECEIVED
JUL 2 3 2004
ENGINEERING
IIiRAnlTE
COnSTRUCTiOn
romPAny sl~SE
July 23, 2004
Reference: Santa Teresa Boulevard Widening Project
Project Number: 04-CDD-128
GCCO Job Number: 201-737
Subject: Lime Treatment Cost Proposal
Charlie,
As previously discussed, please find below Granite Construction Company's proposal for
an alternate pavement section for the Santa Teresa Boulevard Widening Project.
The structural section recommended by Consolidated Engineering Laboratories (see
attached letter) is as follows:
The alternate structural section would result in a cost savings as outlined below:
21 ROADWAY EXCAVATION
N/ALlME TREATMENT
52 ASPHALT CONCRETE
53AGGREGATE BASE
54 FILTER FABRIC
-24,150 CY $3.00
1 LS $368,125.00
-2,384 TON $53.00
-34,229 TON $6.00
-60,000 SY $1.00
TOTAL CONTRACT REDUCTION
-$72,450
$368,125
-$126,352
-$205,374
-$60,000
-$96,051
Weare planning to reclaim the asphalt concrete and aggregate base from the existing
Santa Teresa Boulevard for use in constructing the new structural section. As a condition
to this proposal we are requesting that item number 53 "Aggregate Base" be treated as a
final pay quantity calculated based on the reduced quantity of 32,171 tons at the bid unit
price of $6/ton. Monterey Bay Branch
P.O. Box 720
Watsonville, CA 95077
(831) 763-6100
FAX (831) 763-6121
As outlined in the attached letter from Consolidated Engineering Laboratories the lime
treated subgrade would provide the following benefits:
1. Increased structural strength of the subgrade soil.
2. Stabilization of unstable soil, reducing potential extra work.
3. Minimize the shrink/swell potential of the clayey material.
4. Reduce the effects of water intrusion into the sub grade soil.
5. Reduce the amount of imported and exported material, thus reducing
the impacts of truck traffic on existing city streets.
In the spirit of partnering we are requesting to share in the savings proposed due to the
reduced quantities of material required to construct the project.
If accepted, the alternate pavement section would provide the City of Gilroy with an
improved structural section with the added benefit of an overall cost savings.
Thank you for your consideration of this cost proposal. If there are any questions or
concerns, representatives from Granite Construction Company, Griffin Soil Stabilization
(Lime Treat Contractor), and Consolidated Engineering Laboratories are available to
discuss this issue in further detail.
If you have any questions with regards to this matter please call 831-763-5539.
Thank You,
GRANITE CONSTRUCTION COMPANY
~ JhtV
Steve Walter
Project Manager
~7!22/2004 23:05
9258522254
l:lt-::lI-I-IN ~UIL
r-H\;ll:. tJL
#2'~... .i.dl
~
CONSOLIDATED ENGINEERING'
LABORATORIes
July 23, 2004
Griffin Soil Stabilization and Asphalt
7060 KolI Center Parkway, Suite 324
Pleasanton, California 94566
Attention: Richard Haro
Subjec.t: Alternate p:lvcment RQcommendation~
Santa Teresa Boulevard Widening Project
Gilroy, California
eEL Proposal No. 81-01540
References: 1) Alternative:: povement Sections, ESCNC, August 27,2001
2) Soil Engineering Study Update, ESCNC, February 28, 2001
3) Soil Engineering Study, ESCNC, October 18, 1994
Dear Mr. Haro:
Consolidated Engineering Laboratories (GEL) Geotechnical Division has been requested to provide
pavement recommendations for the subject project. We have reviewed the referenced documents,
and concur with the recommendations contained in these reports. However, we are providing
alternative pavement sections for your consideration to provide, in our opinion, a higher quality
pavemenllhat most likely will be more economic. The recommended alternative pavement section
is:
8 9
5 6
6 6
15 15
26 27
The subgrade soil would be treated with 4 to 5 percent Quicklime Plus based on a soil unit weight of
100 pct. The treatment of the subgrade will provide the following benefits:
. Treatment with a stabilization reagent, such as quicklime or cement, would enhance the
structural strength of the subyrClde soil, thereby increasing the existing R V31ue 5 material to
an R-Value of over 60, This increased R-Value would significantly reduce the overall
pavemp-nt section.
. It is our understanding that the subgrade soil may be unstable and pump under vehicle
loading, and may need to be stabilized. Soil treatmtmL would stabilize the subgrede soil.
. Treetmcnt of the 6ubgradQ soil will minimize thP. !';hrink/swell potential of the onsite clayey
soils. Some of the soil reported in the referenced reports is highly expansive.
7060 Koll Center Parkway, SUite 300. Pleasanton, CA 94566.3108. Tel, 925 485-5000. FAX 925485-5018
'07/22/2004 23:05
'32:,l:lbLL2b4
~I'<:H'r-.l.I'i :::lU.l.1...
c,
GEL Project No. 81-01540
June 23,2004
CONSOLlDA i t:U ENGINEERING
I-ABORATOHIES
. Tre3ted soil is less permeablp. than the onsite soil. and would reduce the effects of water
intrusion into the subgrade soil, which is one of the main causes of pavement failure. As a
result, it will prolong the future life of the pavement.
. Creates a pavement foundation that meets the Strategic Highway Research Program
(SHRr) requirement for Long-Term PavemAnt Performance (L TPP). Perpetual Pavement
Design requires the need for a stable working platform and a consistent roadbed which are
essential to the idea of precluding distress that originate deep in the pavement structure,
. Decreased pavement section would significantly reduce the amount of exported subgrade
soli and impur led baserock to the sitc, which would reduce the amount of traffic on the
streets leading into the project. It would also reduce the stress on the existing roadways,
causing less damage and repairs.
. Treatment will reduce the amount of grading required at the site, since native material will be
utIlIzed more efficiently; thu~ i'eplacing imported matcriol with native material
. Treatment would Clcr:~lp.rate the construction schedule by reducing the amount of grading.
. Current treatment process utilizes specialized equipment and procedures that ensures
quality control throughout the process.
We hope this provides the necessary information for the client to decide on the appropriate
pavement options for this project. If you have any questions, please contact the undersigned at
(925) 485-5000.
Sincerely,
CONSOLIDATED ENGINEERING LABORATORIES
William R. Stevens, PE43010, GE2339
Principal Geotechnical Engineer
DistritJuliun. 3 to AddrelSsee (925/485-55404 Fox 6030)
L:\Users\Geotech\RepPleasanton\81-01540-Sanla Teresa\81-0 1540-ST eresaPaveRecs.doc
2