HomeMy WebLinkAboutGranite Construction - Santa Teresa Blvd. Widening Project - Change Order No. 12 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0450; Fax (408) 846-0429 CHANGE ORDER NO. 12 To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128 Contractor: Granite Construction Company 5/17/2004 Contract Date: This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies fonvarded to Contractor for signature shall be returned to The City of Gilroy properly filled ont. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Descriotion of Work Implement changes to traffic control plan per attached Change Order Request No. lOA. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $8,766.00 Cost $7,448,458.00 -$3,397.00 $7,445,061.00 $8,766.00 $5,369.00 $7,453,827.00 Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price b~A"'" \ rE: Co,..)~onerJ CcN.'Ykt-J'f 1 ff~crOR By: ~ Date: 1J8!P;Z!(J5 ACCEPTED: Date 3.3.D\ Date Date '3/1- /0 s Percentage -0.05% 99.95% 0.12% 0.07% 100.07% COR Granite Construction Company Monterey Bay Branch 580 West .Beach Street Watsonville, CA 95076 Santa Teresa Blvd Widening Project Office Phone: 408-846-9257 Fax: 408-846-9330 CHANGE ORDER REQUEST COR NUMBER: 737-010A Project: Santa Teresa Boulevard Widening Project Project No: 04-CDD-128 To: Charlie Krueger - Resident Engineer City of Gilroy 7351 Rosanna Street Gilroy, CA 95020 From: Steve Walter - Pro.ie~t Manager Date: January 17. 2005 cc: Subject: Traffic Control Changes Charlie, Please find attached daily extra work reports for the implementation of changes to the traffic control plan as outlined in your "Letter #22" and "Letter #25". Changes Per Letters #22 and #~ Additional Linear Ootions Mobilization TOTAL $5,091.00 $3,675.00 S8,766.00 The lump sum amount requested is S8,766.00. f*') I"'. L~;, , J ......~....qf.:::~;;;....... .,~, ..' ....',-.0.. /(j~...-;'" ;;. .. "\" ....~ . : U "I !..:.f53ftt:. :.L ~ ! ! """" ,\ \ : *. ...... - '_ ,I. * . : t ",. J ~f';f ! , .....~ ~i, f ...... .........:.:;............:.y ....:... '. ~ / 00 ........~~.I.~................... (tCitp of~ilrop COMMUNITY DEVELOPMENT DEPARTMENT 7351 Rosanna Street, Gilroy, CA 95020 Planning Division Engineering Division Building, Life & Environmental Safety Division Housing & Community Development (408) 846-0440 FAX: (408) 846-0429 (4Q8) 846-0450 FAX: (408) 846-0429 (408) 846-0430 FAX: (408) 846-0429 (408) 846-0290. FAX: (408) 846-0429 September 2, 2004 Granite Construction Company P.O. Box 720 Watsonville, CA 95077 ATTN: Mr. Steve Walter Letter No. 22 RE: Santa Teresa Boulevard Widening Project No. 04-CDD-128 Traffic Control Changes Reference is made to Letter No. 19 dated August 26, 2004 regarding striping modifications at Santa Teresa at First Street. We have determined that these striping modifications are not necessary at this time. However, we have since identified several safety concerns that must be addressed immediately. You are directed to implement the attached changes as soon as possible. Additional costs for performing this work will be paid at force account. If you have any questions, please do not hesitate to contact me at (408) 846-0410. Sincerely, ~I Resident Engineer cc: City Engineer Don Dey, Transportation Engineer Michael F. Goodhue, Senior Civil Engineer Steven E. Beams, Engineering Technician/Inspector "t:;r~t In _t::anJiI"'CJ fr\ thL:1 I'"'r\rnrn. ,nil'I" TRAFFIC CONTROL CHANGES 1. Relocate stop ahead sign for the westbound to northbound right turn from First to northbound Santa Teresa further east on First Street. 2. Furnish and install additional stop sign on the right and a stop legend for the westbound to northbound right turn from First to northbound Santa Teresa. 3. Extend center line channelizers on the north leg of Santa Teresa closer to the intersection. 4. Add a straight arrow for the northbound Santa Teresa lane on the north side of the First Street intersection. 5. The skip line from the eastbound 152 left turn to northbound Santa Teresa comes off of the incorrect center line. This should be corrected and reflective pavement markers added to both skip lines for the left turns. Existing skip lines do not provide 30' clearance as shown on plans. 6. Add right lane closed signage for the eastbound approaches at Welburn and Longrneadow. Verify at all locations corning into the project that a minimum of three warning signs are visible. (Lane closure signs are acceptable in addition to the road construction ahead and road construction signs.) 7. Low shoulder signs shall be installed for all areas that have a drop. (See the Caltrans Traffic Manual for minimum drop requiring signage.) 8. The barricades require yellow flashers. (The northerly and middle section of the project had no or extremely few flashers.) 9. The delineators require a tighter spacing. Standards.) (See Caltrans 10. Additional reduced speed signs are required. A reduced speed sign should be placed on Santa is corning on to Santa Teresa. Santa Teresa at Welburn a sign north and south of the Welburn Teresa at each point where a driver (Such as for drivers corning on to should be placed on Santa Teresa intersection.) 11. Additional glue down channelizers need to be added to the painted median north of the Mantelli intersection to prevent motorists from entering this median area (at speed) to get to the left turn lane. If the left turn lane can safely be extended that should be the first choice. If there is not adequate room the channelizers need to be placed. ..... ~....qt::~;,;;...... .. A..' .., ""r.'. /(j~"':/ "" "'\..0 \... : i "'.. .c.~~:..L ~ : f ..",,'1' J~ ~ 1 * ~;""-~. ,I * 1 :.... . '-ii' . d : \.' ...........:.....................1"...../ ~ . '. ..........:.'.~.::~................ ({itp of ~ilrop Planning Division Engineering Division Building, Life & Environmental Safety Division Housing & Community Development COMMUNITY DEVELOPMENT DEPARTMENT 7351 Rosanna Street, Gilroy, CA 95020 (408) 846-0440 FAX: (408) 846-0429 (408) 846-0450 FAX: (408) 846-0429 (408) 846-0430 FAX: (408) 846-0429 (408) 846-0290 FAX: (408) 846-0429 September 3,2004 Granite Construction Company P.O. Box 720 Watsonville, CA 95077 ATTN: Mr. Steve Walter Letter No. 25 RE: Santa Teresa Boulevard Widening Project No. 04-CDD-128 Additional Traffic Control Changes In addition to the work specified in Letter No. 22 dated September 2,2004, the right turn lane from westbound First Street to northbound Santa Teresa is to be striped per the attached detail. Additional costs for performing this work will be paid at force account. If you have any questions, please do not hesitate to contact me at (408) 846-0410. Sincerely, LLLJ Charles J. Krueger .. Resident Engineer cc: City Engineer Don Dey, Transportation Engineer Michael F. Goodhue, Senior Ci viI Engineer Steven E. Beams, Engineering Technician/Inspector "Fir.c:t In .C::~rvir.~ tn tht:l r.nmml mit,," , 50' SPACING WITH C30.100 SPACING (TY~.) 25' / , . - - " \ . . .(~\. , , \ \9, 150' 12' . c:> -- --... -- ,. \ lI. 2 .... \ \~ \ \ 01- 0= +c.. I"") C'I~ <I .u ~a (/)<1 \ \ \ \ \ \ \ \ \%