CHANGE ORDER NO. 13
To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CD D-128
Contractor:
Granite Construction Company
Contract Date:
5/17/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be retwned to
The City of Gilroy properly filled out Upon acceptance by the City, the Contractor's copy will be retwned
to him as his authority to proceed with the work
Description of Work
Provide larger crane to place additional soundwall at the southwest corner of Longmeadow Drive and Santa Teresa
Boulevard per attached Change Order Request No. 28.
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percentage
$7,448,458.00
$5,369.00 0.07%
$7,453,827.00
$3,795.00
$9,164.00 0.12%
$7,457,622.00
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $3,795.00
b~ \ -rE c.c.r.JI;~ 1'\ o,..J
~CTOR
BY:~ ~
(~'i~i
Date: fJ3 /O,:l / t:6""
RECOMMENDED BY:
ACCEPTED BY:
~octEn~~
3
Date
3. 3 .(J c(
Date
Date
3/1../os
Date
COR
Granite Construction Company
. Monterey Bay Branch
580 West Beach Street.
Watsonville, CA 95076.
Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257
Fax: 408-846-9330
CHANGE ORDER REQUEST
COR iVUJ~BER: 737-028
Project: Santa Teresa Boulevard W'idening Project
Project No: 04-CDD-128
To:
Charlie KllIeger - Resident Engineer
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Sent Via Fax: ./08-8./6-0./29
From: Steve Walter - Project Manager
Date: January 25_ 2005
cc:
Subject: Larger Crane for Additional Soundwall.
Charlie,
As previously discussed in the field on Wednesday, January 19, 2005, please find below pricing from Sierra Precast to
provide a larger crane to place the additional soundwa)) at the comer of Longmeadow Drive and Santa Teresa
Boulevard.
Crane Upgrade
GCCO Markup
TOTAL
$3,450.00
$ 345.00
$3,795.00
The total lump sum amount requested for this work is $3,795.00.
,
; " ~ "\
,
)
Sen~ By: SIERRA PRECAST INC;
<+OtJi/di.::::>.:;'
..J ell; - t..:,''''' - \..1.,.1 v. ...J-'" '\')
ONE LIVE OAK AVENUE
MORGAN HILL, CA 95031
~ p~, 11ee,
~ S?J~O V
PHONE
(408) 779.1000
P. O. BOX 1240
MORGAN HILL, CA 95038
FAX.
(408) 778.1255
License *369084
A U.S. Concrele Company
January 24, 2005
Mr. Jim Brazil
Granite Construction
P.O. Box 720
Watsonville, California 95077
(831) 763-6100
(831) 763-6121
Reference: SANTA TERESA BL WIDENING (S.P.1. No, 048-04)
Gilroy, California
Change Order Request No. 1
Dear Jim,
We request that the following change(s) be made to the above referenced project's contract.
ADD TO OUR SCOPE OF WORK:
A) Special crane needed to access "additional" wall line at drainage canal.
$ 3,450.00
LUMP SUM
The inclusions, exclusions and conditions of our original contract still remain in effect unless
specifically modified by th'e above change(s).
Should you have any questions regarding the foregoing. please feel free to contact me.
Thank you for your consideration in this matter,
Respectfully yours,
Clzi~
James C. Felice
Chief Estimator
JCF/dg/OS0119(04)
The undersigned client accepts this change order request and authorizes the
commencement of its scope of work.
ACCEPTANCE DATE:
CLIENT SIGNATURE
CLIENT TITLE