HomeMy WebLinkAboutGranite Construction - Santa Teresa Blvd. Widening Project - Change Order No. 18 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0450; Fax (408) 846-0429 CHANGE ORDER NO. 18 To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128 Contractor: Granite Construction Company Contract Date: 5/17/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Implement striping changes at the Santa Teresa BoulevardlFirst Street intersection per attached Change Order Request No. 25. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the tenns of this Change Order for the NET INCREASE of $7,543.00 Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost Percentage $7,448,458.00 $61,170.00 0.82% $7,509,628.00 $7,543.00 $68,713.00 0.92% $7,517,171.00 h eArJ \ '\'C- C.o.J~on ~ Co . ,.4~RACTOR By ~~ Date o3prid) ACCEPTED BY: /' ngineer ! ~A~ Project Engineer COR Granite Construction Company Monterey Bay Branch 580 West Beach Street Watsonville, CA 95076 Santa Teresa Blvd Widening Project Office Phone: 408-846-9257 Fax: 408-846-9330 CHANGE ORDER REQUEST COR NUMBER: 737-025 Project: Santa Teresa Boulevard Widening Project Project No: 04-CDD-128 From: Mike Berg - Project Engineer To: Charlie Krueger - Resident Engineer City of Gilroy 7351 Rosanna Street Gilroy, CA 95020 Date: January 10, 2005 cc: Subject: Striping Extra Work @ First Street Charlie, Please find attached daily extra work reports for the work involved with the additional striping changes at Fil'St Street and Santa Teresa Boulevard. The lump sum amount requested is $19,225.58: 17543 1: o D. at DC ~ ... o ~ t! .. >C III I ~ t: ca a. E o u C o 1- .. U ::s ... .. en c: o U at .. l- I_ CI) .0 CII) E ca g ~ ... ~ .0 (:)S~ ~ ("(') ~ \0 i i i i 1* .... ..... 'ii 0 - .... 0 (I) t- OJ tf (' ~ I- o 3: ~ o c: o +i 'i: CJ Ul CI) C Cl :::i aJ as tJl (I) ~ Q; c t- ~ $ t,) C .... as ::s C/) .9 alj (I) ... en "C (I) .- .J::. ~ ::g lCi5~ ..e-~ (I) ._ ..c:. U. alj 1ii l!! tJl (I) (I) .~ g> Ci5 as c ..c:. c u as Cl ..c:. c o '0. (ij :s 1i) tJl C ti "C CI) E I- o 't CI) a. .! as c ~ ~ o 0 o 0 ~~ NN ~~ o 0 ~ ~ CI) - as C ~ o CI) 0:: C \t') \t') o 0 o 0 ~~ o 0 ~ ~ -- -- ~ ~ I- CI) .0 E :J Z o U U ~ ct) It) It) It) It) en ... 10 en en N ..... M ..... ... CI N ..... M ..... ... 'i CI .... N 0 .... "C C t! C> IGRAnTE mnSTRUCTIDIl 'rnnvmnll SINCE LUlIIrIII CI 1922 DATE PERFORMED 10/22/2004 WORK PERFORMED BY GRANITE CONSTRUCTION COMPANY DESCRIPTION OF WORK Install Channelizers & help with detour change DAILY DETAIL BILLING DATE OF REPORT 1/10/2005 GCCO JOB NO. 201737 Gceo CCO NO. 299519 LABOR CHARGES NAME CRAFT 5T HR5 5T RATE OT HR5 OT RATE NOTE 5UB515TANCE EXT J . Limon CPT 3.00 $34.44 0.00 $0.00 $0.00 $103.32 J . Madrid CPT 3.00 $33.74 0.00 $0.00 $0.00 $101.22 J . Gaither FRM 2.00 $50.64 0.00 $0.00 $0.00 $101.28 TOTAL SUBSISTANCE: $0.00 TOTAL LABOR: $305.82 EQUIPMENT CHARGES r EQUIP NO. T DESCRIPTION REG HRS REG RATE OT HRS OT RATE Att Rate EXT I 06.2247 I PICK-UP 2.00 $12.00 0.00 $0.00 0.00 $24.00 TOTAL EQUIPMENT: $24.00 MATERIAL SUPPLIER United Rentals MATERIAL DESCRIPTION Channelizers UNITS UNIT COST 1.00 $1,583.17 TOTAL MATERIAL: EXT $1,583.17 $1,583.17 SUMMARY ST LABOR ONLY: $305.82 TOTAL EQUIP: $24.00 OT LABOR ONLY: $0.00 TOTAL MATL: $1,583.17 EQUIP OVERHEAD: 15% $3.60 TOTAL LABOR: $305.82 MATL OVERHEAD: 15% $237.48 ST LABOR BURDEN: 18% $55.05 TOTAL EQUIP AND MA TLW/OVERHEAD: $1,848.25 OT LABOR BURDEN: 15% $0.00 TOTAL LABOR + BURDEN: $360.87 SUBSISTENCE $0.00 TOTAL LABOR, EQUIP & MA TL W/OVERHEAD: $2,328.20 LABOR OVERHEAD: 33% $119.09 BOND COST 2% $46.56 TOTALLABOR+BURDEN+OVERHEAD: $479.95 TOTAL DETAIL BILLING: $2,374.76 GRANITE REPRESENTATIVE ACCEPTED FOR PAYMENT EWID: 551 Page 1 of 1 'IGRAnTE mnSTRUCTIDIl rlln'Ull'lnl I SINCE LUlIIrIII CI 1922 DATE PERFORMED 10/22/2004 WORK PERFORMED BY GRANITE CONSTRUCTION COMPANY DESCRIPTION OF WORK Restriping changes at First Street & Santa Teresa BLVD. DAilY DETAil BilliNG DATE OF REPORT 1/10/2005 GCCO JOB NO. 201737 GCCO cco NO. 299519 MATERIAL CHARGES MATERIAL SUPPLIER MATERIAL DESCRIPTION Giacalone Electric Inc. in COR 36 Move Signal heads @ Fir Linear Options, Inc. Restriping @ First Street UNITS UNIT COST EXT 1.00 $4,922.27 TOTAL MATERIAL: $4,922.27 -$7,476.97 4-922.27 SUMMARY ST LABOR ONLY: $0.00 TOTAL EQUIP: $0.00 OT LABOR ONLY: $0.00 TOTAL MATL: $7,416.97 EQUIP OVERHEAD: 0% $0.00 4?Z.2,Z7 TOTAL LABOR: $0.00 MATL OVERHEAD: 5% $373.86 2.46, II ST LABOR BURDEN: 0% $0.00 TOTAL EQUIP AND MATLW/OVERHEAD: ~7,85B.82 OT LABOR BURDEN: 0% $0.00 !::> /68.38 $0.00 TOTAL LABOR + BURDEN: SUBSISTENCE $0.00 rrOTAL LABOR, EQUIP & MATL W/OVERHEAD: $7,859.82- LABOR OVERHEAD: 0% $0.00 0% $0.00 TOTAL LABOR+BURDEN+OVERHEAD: $0.00 TOTAL DETAIL BILLING: $7,859.82 5/6'8,38 GRANITE REPRESENTATIVE ACCEPTED FOR PAYMENT EWID: 553 Page 1 of 1