HomeMy WebLinkAboutGranite Construction - Santa Teresa Blvd. Widening Project - Change Order No. 30 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0450; Fax (408) 846-0429 CHANGE ORDER NO. 30 To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128 Contractor: Granite Construction Company Contract Date: 5/17/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies fOlWarded to Contractor for signature shall be returned to The City of Gilroy properly filled out Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Construct storm drain Laterals F-l and F-3 at force account and field adjust Lateral A-IO per attached Change Order Request No. 38 and Letter No. 46. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $10,036.00 Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost $7,448,458.00 $117,218.00 $7,565,676.00 $10,036.00 $127,254.00 $7,575,712.00 P.M. Percentage Initial 1.57% d.1 1.71% ~ b~\~ ~~c.;n0t-l ~7~f ~NJRAC;OR By: ~ Date: f~~ {!iAru~ek RECOMMENDE 5/4/1:;5 Date s-s-.o<{' ACCEPTED BY: COR Granite Construction Company Monterey Bay Branch 580 West Beach Street Watsonville, CA 95076 Santa Teresa. Blvd Widening PrQject Office Phone: 408-846-9257 Fax: 408-846-9330 CHANGE ORDER REQUEST COR NUMBER: 737-038 Project: Santa Te,'esa Boulevard Widening Project Project No: 04-CDD-128 To: Charlie Kl1leger - Resident Engineer City of Gilroy 7351 Rosanna Sh-eet Gilroy, CA 95020 From: Mike Berg - Project Engineer Date: March 14.2005 cc: Subject: Field Fit RCP Storm Drain. Chal'lie, Please find attached daily extra work reports for the field adjustments required to construct storm dl'ain lateral F-l, F-3 and A-tO. The attached exh'a wOI'k bills represent wOI'k pel'fol'med between Octo bel' 4th, 2004 and Octobel' 28th, 2004, . $ The lump sum amount requested IS $19,141.00:. IQ 036 cu - o I- f'.. ~ \0 C'f) 0- C\J ili;~i .... ~ ~ iA- iA- Ii \() 0--- lri i~ .... ..... o (b OJ ~ ,... M ,... 'i en ~ .... 1: I I Q - u.. u.. N 0 (tj ~ t- o .... "C (IJ (IJ c: - - e a. ~ ~ en ~ ~ I c: .!: I u.. I ~ C> G) u.. u.. ~ "(ij ttl (tj (tj ~ "*' .... .... .... at: -0 -0 .... (IJ fD E E (IJ - (IJ U ,... - ttl - .... .... .... ~ ....J ~ @ II) ~ 0 0 .... .... .... en ~ 1ii 1ii 0 0 0 c: en ... - - - N .. 0 .... .... en en en .~ 0 0 0 ~ - - ....J ....J ....J -0 (/) (/) U U U ~ .... (IJ (IJ E 0 -0 -0 0.. 0.. 0.. .... f! f! u u u 0 c: 1ii ~ 0 01 01 0::: 0::: 0::: .... .. 1ii - 0 (/) Lo Lo Lo :::::s :::::s - .. "C :0- :0- ~ ~ (/) - - - (IJ >C (.) ttl ttl 0 0 0 -0 iii ol:l ol:l i:o ~ ;;... f! (I.l III c (IJ (IJ ~ N N OJ (5 (5 (tj 1ii .r:::. .r:::. ttl ttl :::::s I - - - - 1ii :0- 0 0 (/) (/) 0.. 0.. c: c: c: <( ~ "C I: G) ca E 0 ~ a. t ~ ~ ~ ~ ~ 0 G) 0 0 0 0 0 0 E 0 0 0 0 0 ~ a. ~ ~ ~ ~ N -- eo G) ~ LO ~ r- eo ~ ... -- -- -- 0 CU 0 0 0 0 0 0 C ..... ~ ~ ~ ~ ~ U s I: CU c 0 t= LO LO LO LO LO LO 0 0 0 0 0 0 0 0 0 0 0 0 0 .- ~ ~ ~ ~ ~ ~ .. G) ~ ~ ~ ~ ~ ~ U a:: -- -- -- ~ ~ ~ ~ ~ ~ :s c .. LO <<> r- eo Q) 0 N N N N N en .. '- LO LO 1.0 1.0 1.0 1.0 en G) .Q I: E ,... ::::I .... II) 0 Z en 0 en U N U U ~ .. '- G) .- .Q ,... 1:1.1) E M ,... cag ::::I .... Z 0 ..~ N .Q ,,~ 0 '"") (lCitp of <tPtlrop. COMMUNITY DEVELOPMENT DEPARTMENT 7351 Rosanna Street, Gilroy, CA 95020 Planning Division Engineering Division Building, Life & Environmental Safety Division Housing & Community Development (408) 846-0440 FAX: (408) 846-0429 (408)846-0450 .FAX: (408) 846-0429 (408) 846-0430 FAX: (408) 846-0429 (408) 846-0290 FAX: (408) 846-0429 October 11, 2004 Granite Construction Company P.O. Box 720 Watsonville, CA 95077 ATTN: Mr. Steve Walter Letter No. 46 RE: Santa Teresa Boulevard Widening Project No. 04-CDD-128 Storm Drain Conflicts (Lat F-l & F-3) We are in receipt of your letter dated October 4,2004 regarding existing utilities in conflict with the storm drain system. As agreed last week, installation of Laterals F-l and F-3 will be paid at force account. Since only minor adjustments were required to install Laterals E-3, E-4, F- 7 and F-8, these will be paid under the associated bid items. Installation of all catch basins and manholes will also be paid under the associated bid items. If you have any questions, please do not hesitate to contact me at (408) 846-0410. Sincerely, ~-:rJ Resident Engineer cc: City Engineer Don Dey, Transportation Engineer Michael F. Goodhue, Senior Civil Engineer Steven E. Beams, Engineering Technician/Inspector "First In Service to the Community"