CHANGE ORDER NO. 52
To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128
Contractor:
Granite Construction Company
Contract Date:
5/17/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies fOlWarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Furnish and install root barrier per attached Change Order Request No. 77 A and Letter No. 189 dated
October 5, 2005.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. Consideration oftime adjustment will be deferred until receipt of a Time Impact Analysis in
accordance with Section 01310-6.0 of the Contract Documents.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $15,681.00
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$7,448,458.00
$234,663.00
$7,683,121.00
$15,681.00
$250,344.00
$7,698,802.00
P.M.
Percentage ~
3.15%~
3.36% d-J{
6rtl/l,f~ ~~~:4/1' tb"'{PN7Y
~OR
By: Date: 1/ Jg / !to-
ClareACL 3a~~
ACCEPTED BY:
/~ 2J)~
Date
II/z- r ~f
Date
11/3/2005
'COR.
CHANGE .oRDER REQUEST
COR NU;WBE/J: 737-077 A
Granite C.onstruction .Company
Monterey Bay Branch .
580 West Beach Street
Watsonville, CA 95076 .
Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257 .
Fax: 408-846-9330
Project:. Santa Te."esa Boulevard Widening P."oject
Project No: 04-CDD-128
To:
Charlie Krtiege.. - Resident Enginee..
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
From: Mike Berg - Project Engineer
Date: October 11. 2005
cc:
Subject: Revised Root Ba....ie.. Cost P..oposal.
Charlie,
Please find below ou.. ..evised p..ice to install mot ba....ie.. at the 53 oak t..ees specified along with 5 t..ees at the
cu..b side. This cost p..oposal shall take the place of COR #77.
B&B Landscape Cont..acto..s Inc. (see attached)
GCCO Ma..kup (10%)
TOTAL
$ 14,255.00
$ 1.425.50
$ 15,680.50
The total lump sum amount requested for this work is $ 15,681.00
. -)
10/10/2005 07:46
4085738343
8&8 LANDSCAPE
PAGE 01/01
B&B
October 10, 2005
Granite COIl!;tructiol1 Co.
Attcntion:
Stcve Walter
Project:
Santa Teresa Blvd. Widening
We have received a copy of the letter from the City of Gilroy regardIng the 18" root
barrier installation. We will install the barriers at all of the Oak trees, (53) trees on both
sides and at (5) trees at the curb side.
III sections ($I05.00/section)
Install the barriers between the electrical boxes & concrete
Total Change Order Request
$11.655,00
2.600.00
$14.~S5J!O
The City's Jetter states that only the 36" box trees require the tree toot barriers. Does this
mean none of the remaining trees will get root barriers? Or do we follow the detail on
Drawing PL-2? Please Jet me know.
If YOll bave any questions please contact my office.
Thank you,
B & B LANDSCAPE CONTRACTORS, INC.
~/~-
Relnll'Okf'Bnml1
Vice President
~
RB~.l1l1
Tr~ll~lmttecl viA fAX
Page I of 1
450 Phelan Ave. San Jose,CA 95112.2504 (408) 573-9430 Fax(408).673-8343
ConttactorsLic.352633'
.'1'
';"" 'I",
..., I',
qcitp Qf ~ilro!,
COMlVlUNITY DEVELOPlVIENT DEPARTMENT
73S I Rosanna Street. Gilroy. cA 95020
Planning Division
Engineering Divis.ion
Building, Life & Environmental Safety Division
Housing & Community Development
(408) 846-0440 FAX: (408) 846-0429 .
(408) 846-0450 FAX: (408) 846-0429
(408) 846-0430 FAX: (408) 846-0429
. (408) 846-0290 FAX: (408) 846-0429
. October 5, 2005
Granite Construction Company
P.O. Box 720
Watsonville, CA 95077
ATTN: Mr. Steve Walter
Letter No. 189
RE: Santa Teresa Boulevard Widening Project No. 04-CDD-128
Root Barrier Cost Proposal
We are in receipt of Change Order Request No. 77 dated October 4, 2005 providing
a cost proposal for furnishing and installing root barrier per RFI #41. We have
determined that only the 36" box trees require root barrier. There are 53 trees in the
median that will require root barrier on both sides, and 5 trees on the west side that
will require root barrier adjacent to the curb.
Please proceed with installation of 18" root barrier. A change order will be issued in
the amount of $15,681.00. This includes the cost to remove and reinstall the
electrical boxes in the' median.
If you have any questions, please do not hesitate to contact me at (408) 846-0410.
Sincerely,
~:-j )I~~
Resident Engineer
cc: City Engineer