HomeMy WebLinkAboutGranite Construction - Santa Teresa Blvd. Widening Project - Change Order No. 53 6 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0450; Fax (408) 846-0429 CHANGE ORDER NO. 53 To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128 Contractor: Granite Construction Company Contract Date: 5/17/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Upgrade Battery Backup System to PBM-2000 and mount in a "sidecar" battery compartment on the traffic signal controller cabinets at the Santa T eresaIW elburn Avenue and Santa T eresalLongmeadow Drive intersections per attached Change Order Request No. 61. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the tenus of this Change Order for the NET INCREASE of $9,614.00 Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost $7,448,458.00 $250,344.00 $7,698,802.00 $9,614.00 $259,958.00 $7,708,416.00 P.M. Percentage Initial 3.36% ~ 3,49% ~ 0rMfl6 ;5;/It5l7udh/l '~A1/AI7r ~ ~ Date: liP/IllS CI al't~UA- ff>aJ-ub- ACCEPTED BY: ~ I / /2-,t/. J Date RECOMMENDED BY: 11/14/2005 COR NUMBER: 737-061 Granite Construction Company . Monterey Bay Branch 580 West Beach Street Watsonville, CA 95076 . Santa Teresa Blvd Widening Project Office Phone: 408-846-9257 Fax: 408-846-9330 .COR .CHANGE ORDER REQUEST Project: . Santa Teresa Boulevard Widening Project Project No: 04-CDD-128 To: Charlie Kroeger - Resident Engineer City of Gilroy 7351 Rosanna Street Gilroy, CA 95020 Sent Via Fax: 408-846-0429 From: Steve Walter - Project Manager Date: June 29, 2005 cc: Subject: Upgrade battery backup system and add "sidecar" compartment. Charlie, Please find below our proposal in response to your "letter number 146"0 Giacalone Electrical Services (see attached quote) GCCO Markup (10%) TOTAL $8,740.00 $ 874.00 $9,614.00 The total lump sum amount requested (or this work is $9,614.00. n El\l ING Giacalone DESIGN * CONSULTING * INSTALLATION * SERVICE ELECTRICAL SERVICES. INC; LICENSE NO. 540448 ~300 MONTEREY ROAD * GILROY, CALIFORNIA 9502.0 * Office: (408) 842.9655 * Fax: (408) 842-5285 Date: June 28, 2005 Job# : COR#: Company: Granite Construction Office: Attn : Steve Walter Fax: Job: Santa Teresa Widening Project Mobile: Scope Of Work: Install Sidecar Cab. For BBS. Upgrade BBS to PBM-2000. 599-1 COR-17 (831) 763-6100 (831) 763-6121 (831) 750-0400 From: Tim Atkins Mobile Phone: (408) 591-1364 * * Change Order * * Our price includes required labor, tools, material, insurance and supervision for th following work. Permits excluded. 2 EA Upgrade BBS to PBM-2000 add sidecar cab. @ $3,800.00 = $7,600.00 Total: GESI Mark Up: Total: $7,600.00 $1,140.00 $8,740.00 NOTES: 1) Bid based on prevailing wage rates. 2) Bid based on 8 hour work days Monday - Friday. Overtime is extra. 3) Bid is only for new BBS at Welburn Ave. and Longmeadow Dr. 4) Bid includes Installation and turn on support from JAM Services. 5) Material has a 4 week lead time. Accepted Signature I Title Date * * PLEASED SIGN AND FAX BACK APPROVED COPY TO TIM ATKINS @408-848-1130 * *