CHANGE ORDER NO. 53
To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128
Contractor:
Granite Construction Company
Contract Date:
5/17/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Upgrade Battery Backup System to PBM-2000 and mount in a "sidecar" battery compartment on the traffic signal
controller cabinets at the Santa T eresaIW elburn Avenue and Santa T eresalLongmeadow Drive intersections per
attached Change Order Request No. 61.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
I (We) agree to make the above change
subject to the tenus of this Change Order
for the NET INCREASE of $9,614.00
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$7,448,458.00
$250,344.00
$7,698,802.00
$9,614.00
$259,958.00
$7,708,416.00
P.M.
Percentage Initial
3.36% ~
3,49% ~
0rMfl6 ;5;/It5l7udh/l '~A1/AI7r
~
~ Date: liP/IllS
CI al't~UA- ff>aJ-ub-
ACCEPTED BY:
~
I / /2-,t/. J
Date
RECOMMENDED BY:
11/14/2005
COR NUMBER: 737-061
Granite Construction Company .
Monterey Bay Branch
580 West Beach Street
Watsonville, CA 95076
. Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257
Fax: 408-846-9330
.COR
.CHANGE ORDER REQUEST
Project: . Santa Teresa Boulevard Widening Project
Project No: 04-CDD-128
To:
Charlie Kroeger - Resident Engineer
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Sent Via Fax: 408-846-0429
From: Steve Walter - Project Manager
Date: June 29, 2005
cc:
Subject: Upgrade battery backup system and add "sidecar" compartment.
Charlie,
Please find below our proposal in response to your "letter number 146"0
Giacalone Electrical Services (see attached quote)
GCCO Markup (10%)
TOTAL
$8,740.00
$ 874.00
$9,614.00
The total lump sum amount requested (or this work is $9,614.00.
n
El\l
ING
Giacalone
DESIGN
* CONSULTING
*
INSTALLATION
* SERVICE
ELECTRICAL SERVICES. INC; LICENSE NO. 540448
~300 MONTEREY ROAD * GILROY, CALIFORNIA 9502.0 * Office: (408) 842.9655 * Fax: (408) 842-5285
Date: June 28, 2005 Job# :
COR#:
Company: Granite Construction Office:
Attn : Steve Walter Fax:
Job: Santa Teresa Widening Project Mobile:
Scope Of Work: Install Sidecar Cab. For BBS. Upgrade BBS to PBM-2000.
599-1
COR-17
(831) 763-6100
(831) 763-6121
(831) 750-0400
From: Tim Atkins
Mobile Phone: (408) 591-1364
* * Change Order * *
Our price includes required labor, tools, material, insurance and supervision for th following work.
Permits excluded.
2
EA Upgrade BBS to PBM-2000 add sidecar cab.
@ $3,800.00 =
$7,600.00
Total:
GESI Mark Up:
Total:
$7,600.00
$1,140.00
$8,740.00
NOTES:
1) Bid based on prevailing wage rates.
2) Bid based on 8 hour work days Monday - Friday. Overtime is extra.
3) Bid is only for new BBS at Welburn Ave. and Longmeadow Dr.
4) Bid includes Installation and turn on support from JAM Services.
5) Material has a 4 week lead time.
Accepted
Signature I Title
Date
* * PLEASED SIGN AND FAX BACK APPROVED COPY TO TIM ATKINS @408-848-1130 * *