CHANGE ORDER NO. 61
To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128
Contractor:
Granite Construction Company
Contract Date:
5/17/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Hand dig streetlight foundations at three locations, install three R13 signs on traffic signal poles and place slurry cap
over quad duct per attached Change Order Request Nos. 68 & 71.
All requirements of the original Contract Docmnents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $3,963.00
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$7,448,458.00
$302,077.00
$7,750,535.00
$3,963.00
$306,040.00
$7,754,498.00
P.M.
Percentage Initial
4.06% cA-{
4.11% d-{
6ralJ,fr., tof715fn~n()r" ~fJMr
~N~CTOR
BY:~ Date: 01/03/01:,
~/ar~Sa/c.od.A
RECOMMENDED BY: ~LL ~;2 ~~-
C~~"'L7 '-o~~
1/1-/ob
Date
ACCEPTED BY:
Date
12/12/2005
CHANGE ORDER ~QUEST
COR NUMBER: 737-068'
. Granite C<mstruction,Company
Monterey Bay Branch , .....
. 580 West Beach Street .
Watsonville, CA 95076
Santa Te~ Blvd Widening Project Office
Phone: . 408-846-9257 .
. Fax: 408-846~9330
COR
. Project: Santa Teresa Boule,,'ard Widening Project
Project No: 04-CDD-128
From: StCYC Waltcr - Project Manager
To:
Charlie Krueger - Resident Engineer
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Sent Via Fax: .108-8./6-0./29
Dale: July' 28, 2005
cc:
Subject: Hand Digging of Street Light Foundations.
Charlie,
Please find below Giacalone Electrical Services T &M billing for hand digging street light foundations due to various
conflicts.
Giacalone Electrical Services (see attached )
GCCO Markup (100/0)
TOTAL
II 33,39
113,34-
, ~J .. ""3
J(~;t6,('
$1)99.2"
50 139.&2-
$1,529.J(;
The total lump sum amount requested for this work is $1~19,QQ;
4 J24 7.00
\.
". GIACALONE ELECTRICAL SERVICES, INC. .
(408) 842-9655 * FAX (408) 842-5285
. L1C #: C10/A 540448
CO / WO # :
19 A
REVISION:
1
COMPANY: Granite Construction
ADDRESS: 580 West Beach St.
CITY, ST, ZIP Watsonville, CA 95077
OFFICE:
FAX:
MOBilE:
(831) 763-6100
(831) 763-6121
(831) 750-0400
SUPERINTENDENT DAYS TO COMPLETE WORK
Tim Atkins ASAP
GESI JOB NUMBER DATE
599-1 November 18,2005
GESI JOB NAME REQUESTED START.DATE
Santa Teresa Widening ASAP
JOB lOCATION REQUESTED COMPLETE DATE
Gilrov. CA ASAP
REQUESTED BY: Steve Walter I Charlie Krueger
QTY MATERIAL PRICE UM AMOUNT DESCRIPTION OF WORK
Hand dig holes for street light foundations in locations where
sound-wall is to close to curb and gutter to drill holes in proper
locations. The station #'s are 32+10, 33+30, and 34+50.
EQUIP I OTHER. HRS UNIT QTY RATE AMOUNT
Service Truck 8.00 EA 1 $15.00 $120.00
SUBTOTAL - OTHER $120.00
15.00% MARKUP-OTHER $18.00
TOTAL - OTHER $138.00
LABOR HRS UNIT QTY RATE AMOUNT
Foreman 2.00 EA 1 $48.48 $96.96
Laborer 8.00 EA 2 $35.14 $562.24
SUBTOTAL - MATERIALS SUBTOTAL-LABOR $659.20
8.25% TAX - MATERIALS 18.00% MARKUP-LABOR $118.66
15% MARKUP - MATERiALS 33.00% SURCRG . LABOR $217.54
TOTAL - MATERIALS TOTAL - LABOR $995.39
Signature
TOTAL LABOR $995,39
TOTAL MATERIALS
TOTAL EQUIP/OTHER $138,00
7~1tM I TOTAL> $1,133.39
By signing this work order, you are only acknowledging that the material, labor, equipment
and other quantities and hours are accurate and have been completed. Pricing of this work
order will be done according to contract / service rates by the main office.
I here by acknowledge the satisfactory completion of the above described work.
/
/
/
COR
Granite.'Const~c.tion Company' .
MOflJerey. Bay Branch
580 West Beach Street
VIIatsonville.. CA 95076 .
. Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257 .
Fax: . 408-8'46~9330
(RANGE ORDER REQUEST
COR NUMBER: 737-071
Project: . Santa Teresa Boulevard Widening Project
Project No:04-CDD-128
To:
Cha"'ie Kruegel' - Resident Engineer
City of Gilroy
7351 Rf)sanna Street
Gilroy, CA 95020
Fi'om: Mike Berg - Pi'oject Engineer
Date: August 12, 2005
cc:
Subject: R13 Sign InstaJlation & Slurry Cap.
Chal"lie,
Please find below Giacalone Electric Services T &M Billing for the installation of three R13 signs on existing
signal poles and the additional slurry cap poured over the new quad duct in five shallow locations.
Giacalone Electrical Services (see attached)
GCCO Markup (5%)
TOTAL
2586.35
} 2. 9.32
27/5,67
$ 3,999.71
S J99.97
!Ii 3,319.68
The total lump sum amount requested for this work is S 3,311.99
$27/6,00
J
GIACALONE ELECTRICAL SERVICES, INC.
(408) 842-9655 .. FAX (408) 842-5285 .
L1C #: C10/A 540448
CO / WO # : 70307 C-15 REVISION:
1
COMPANY: Granite Construction
ADDRESS: 580 West Beach St.
CITY, ST,. ZIP Watsonville, cA 95077
OFFICE:
FAX:
MOBilE:
(831) 763-6100
(831) 763.6121
(831) 750-0400
SUPERINTENDENT DAYS TO COMP.LETE WORK .'
Tim Atkins ASAP
GESI JOB NUMBER DATE
599.1 November 18,2005'
GESI JOB NAME REQUESTED START DATE
Santa Teresa Widening ASAP
JOB lOCATION REQUESTED COMPLETE DATE
Gilroy, CA ASAP
REQUESTED .BY: Steve Walter I Charlie Krueger
QTY MATERIAL PRICE UM AMOUNT DESCRIPTION OF WORK
18 3/4" Stainless Steel Strap $0.75 Ft $13.50 Hang "No Right Turn On Red" signs on traffic signal poles at 3
6 Flared Leg Brackets $2.19 ea $13,14 locations.
6 Stainless Steel Banding Buckels $1.29 ea $7,74
EQUIP / OTHER HRS UNIT QTY RATE AMOUNT
Service Truck 2.00 EA 1 $15.00 $30.00
r Basket Truck 125 ~.50 EA 1 $23.00 $80.50
SUBTOTAL.OTHER $110.50
15.00% MARKUP-OTHER $16.58
TOTAL - OTHER $127.08
LABOR HRS UNIT QTV' . AATE:' AMOUNT
Foreman 2.00 EA 1 $48.48 $96.96
Basket Truck Operator 3.50 EA 1 $46.84 $163.94
SUBTOTAL - MATERIALS $34.38 SUBTOTAL-LABOR $260.90
8.25% TAX - MATERIALS $2.84 18.00% MARKUP-LABOR $46.96
15% MARKUP - MATERIALS $5.58 33.00% SURCRG - LABOR $86.10
TOTAL - MATERIALS $42.80 TOTAL -LABOR $393.96
By signing this work order, you are only acknowledging that the material, labor, equipment
and other quantities and hours are accurate and have been completed. Pricing of this work
order will be done according to contract / service rates by the main office,
TOTAL LABOR $393.96
TOTAL MATERIALS $42.80
TOTAL EQUIP/OTHER $127.08
7~1t~ I TOTAL> $563.83
Signature
I here by acknowledge the satisfactory completion of the above described work,
":'ACALONE ELECTRICAL SERVICES, INC.
(408) 842.9655 * FAX (408) 842-5285
LIC #: C10/A 540448
CO 1 WO # : 58913 C-16 REVISION:
1
COMPANY: Granite Construction
ADDRESS: .580 West Beach St.
CITY, ST, ZIP Watsonville, CA 9.5077
OFFICE:
FAX:
MOBILE:
(831) 763-6100
. (831) 763-6121
(831) 750-0400
SUPERINTENDENT DAYS TO COMPLETE WORK
Tim Atkins ASAP
GESI JOB NUMBER DATE
599.1 Novembe'r 18,2005
GESI JOB'NAME REQUESTED START DATE
Santa Teresa Widening ASAP
JOB LOCATION REQUESTED COMPLETE DATE
Gilroy, CA ASAP
REQUESTED BY: Steve Walter I Charlie Krueger
QTY MATERIAL PRICE UM AMOUNT DESCRIPTION OF WORK
9 Slurry Mix $105.00 Yrd $945.00 Install Quad-Duct over culverts south 0 f Longmeadow Dr.
Slurry cap shallow conduits
EQUIP / OTHER HRS UNIT QTY RATE AMOUNT
1 Ton EXTD cab diesel 4.00 EA 1 $15.00 $60.00
Backhoe 597 2.00 EA 1 $26.00 $52.00
SUBTOTAL - OTHER $112.00
15.00% MARKUP. OTHER $16.80
TOTAL - OTHER $128.80
LABOR HRS UNIT QTY .RATE AMOUNT
Foreman 4.00 EA 1 $48.48 $193.92
Laborer 4.00 EA 2 $35.14 $281.12
SUBTOTAL - MATERIALS $945.00 SUBTOTAL-LABOR $475.04
8.25% TAX - MATERIALS $77.96 18.00% MARKUP.LABOR $85.51
15% MARKUP - MATERIALS $153.44 33.00% SURCRG - LABOR $156.76
TOTAL - MATERIALS $1,176.41 TOTAL - LABOR $717.31
By Signing this work order, you are only acknowledging that the material, labor, equipment
and other quantities and hours are accurate and have been completed. Pricing of this work
order will be done according to contract I service rates by the main office,
TOTAL LABOR $717.31
TOTAL MATERIALS $1,176.41
TOTAL EQUIP/OTHER $128.80
7~1tM I TOTAL> $2,022.52