HomeMy WebLinkAboutGranite Construction - Santa Teresa Blvd. Widening Project - Change Order No. 77
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846-0450; Fax (408) 846-0429
CHANGE ORDER NO. 77
To contract for: Santa Teresa Blvd. Widening Project, Project No, 04-CDD-128
Contractor:
Granite Construction Company
Contract Date:
5/17/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Perform additional landscaping and irrigation work at Oak Tree Comer and Longmeadow Drive per attaehed Change
Order Request No. 119.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order, The contract time shall be extended by five (5) working days,
By:
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$7,448,458.00
$399,327,00
$7,847,785,00
$8,466,00
$407,793,00
$7,856,251,00
P,M,
Percentage Initial
5,36% ~
5.47% ~
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $8,466.00
Date: OS!O;<./Ob
0-/5 ,06
ACCEPTED BY:
Date
c CO--
f\- C\ir' Lr-
City Engineer
~j~t~
)-1 j-O b
Date
S- k/ W;
Date
411712006
GRANITE CONSTRUCTION Fax:4088428658
Apr 5 '06 13:32
P.02
COR
CHANGE ORDER REQUEST
COR NUMBER: 737-119
Granite Construction Company
Monterey Bay Branch
580 West Beach Street
Watsonville, CA 95076
Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257
Fax: 408-846-9330
Project: Santa Teresa Boulevard Widening Project
Project No: 04-CDD-128
To:
Charlie Krueger - Resident Engineer
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
From: Mike Berg - Project Engineer
Date: April 5, 2006
cc:
Subject: Additional Landscaping & Irrigation Pricing,
Char1ie~
Please find attacbed 8&B pricing for the extra work requested by the City of Gilroy in Letter No. 207. An
additional 5 working days are requested for the performance of this work.
B&B Landscaping
A, 1st Street Driveway & Oak. Corner Extra work
B. Repair Lawn @ 1st Street
C. Longmeadow Park Strip Extra Work
GCC Markup ( 10% )
TOTAL
$ 3,182.00
$ 2,774,00
$ 1,740,00
S 769.60
$ 8,465.60
The lump sum amount requested for tbis extra work is S 8,466.00
B&B
CikHN11 c. CUNS fRUCTION Fax:4088428658
Apr 5 '06 13:33
P.03
Granite Construction
Gilroy Job Trailer
Attn: Mike Berg / Steve Walter
Project: Santa Teresa Blvd. Widening
Proposal for miscellaneous landscape and irrigation work.
The ittea on Santa. Teresa and First Street at the driveway and the Oak tree.
Relooate the apartment sign with 2 new posts and hardware.................. .$950.00
12 hours labor to regrade the area........ ....... ..... .... ... ... ....................$816.00
2 hours labor to adjust the 3 valve boxes... ................................. ......$136.00
Add 4 new sprinklers............................................................ ....$260.00
4 flats English Ivy groundcovers..,.. .................................. ..... .... ...$180.00
6 ou. yds. mulch at the entire Oak. tree area...... __. n............... .......... ....$39Q.OO
6 hours foreman supervision and pickup materials... .........,.. ...............$450.00
1r()~I..................................................................................S:5,l~.~
Repair the lawn at the corner on First Street damaged by P. G. & E., based on 300 sq. ft.
Irrigation work has been completed by B & B.
4 homs foreman. ............ t. t .......".. ......"..... ... ... ... .., ....... ......... ......... ......$300.00
16 hours labor......... ......... ............ ...... ..... ................... ........ ....$1,088.00
6 pop-up sprinklers with pipe and fittings.............. ............... ......,......$150,00
8 hours labor to re-grade and soil prep..... ............. ............ ......... ......$544.00
4 hours labor install sodded lawn..................... . .............. ........... ....$272.00
4 hours foreman supervision and pickup materials... .................. ...... ....$300.00
300 sq. ft. sodded lawn,...........,. ..,.. ................. ....................... ....$120.00
Total....... ...... ............ ..................... ...................... ...... ............... .52,774..00
The two sides on Longmeadow park strips and at the service gate.
16 hours labor to re-grade and soil prep. .................................. ......$1,088.00
11 - 5g Raphiolepis Ovata........... ......... ................................... ...$242.00
5 - 5g Coprosma Kirkii.......... .... ............................. '_' ""'''''''''' ...$110.00
4 hours foreman supervision and pickup materials..................... ........ .$300.00
Total..... ....,..... ..... ..... .... ...... ............. ..... .................................. .SI,740.00
Very Truly Yours, ,
B & B Landscape Contractors, Inc.,
Reinhold Brunn
RB: mw
450 Phelan AVe. San Jose, CA 95112-2504 (408) 573-9430 Fax (408) 573,8343
Contractors Uc. 352633