CHANGE ORDER NO. 83
To contract for: Santa Teresa Blvd. Widening Project, Project No. 04-CDD-128
Contractor:
Granite Construction Company
Contract Date:
5/17/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Perfonn landscaping and irrigation extra work per attached Change Order Request No, 117, and furnish and install
galvanized steel pipe at the booster pump per attached Change Order Request No. 122.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order, The contract time shall not extend unless expressly provided for in this Change Order. By signing this
Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full
satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change
Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of
efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work,
ACCEPTED BY:
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$7,448,458.00
$662,159.00
$8,110,617,00
$8,317,00
$670,476,00
$8,118,934.00
P.M,
Percentage Initial
8.89% M .
9,00%M
I (yVe) agree to make the above change
subject to the tenns of this Change Order
for the NET INCREASE of $8,317.00
By:
Date: O:Z/:27/Zoo7
RECOMMENDED BY:
ngineer
p. E/
roJect ngmeer
Date
112/2007
~COR
COR NUMBER: 737-117
Granite Construction Company
Monterey Bay Branch
580 West Beach Street
Watsonville, CA 95076
Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257
Fax: 408-846-9330
CHANGE ORDER REQUEST
Project: Santa Teresa Boulevard Widening Project
Project No: 04-CDD-128
To:
Charlie Kroeger - ~ident Engineer
City of Gilroy
7351 Rosanna Sh.eet
Gilroy, CA 95020
From: Mike Berg - Project Engineer
Date: March 15,2006
cc:
Subject: Landscaping & Irrigation Extra Work.
Charlie,
Please find attached daily extra work reports from B&B Landscaping for work requested by the City of Gilroy.
B&B Landscaping (See Attached)
A. Install Drainage Line at Sound wall
B. Install Irrigation Sleeve at Mantelli Sidewalk
C. Break Out Cement Treated Base in Median
GeC Markup ( 5% )
TOTAL
$ 950.00
$ 1;389.00
$ 2,830.00
$ 258.45
$ 5,427.45
The lump sum amount requested for this extra work is $ 5,427.00
l""""-
"...."
MAR 1 2005
COR
Granite Construction Company
Monterey Bay Branch
580 West Beach Street
Watsonville, CA 95076
Santa Teresa Blvd Widening Project Office
Phone: 408-846-9257
Fax: 408-846-9330
CHANGE ORDER REQUEST
COR NUMBER: 737-122
Project: Santa Teresa Boulevard Widening Project
Project No: 04-CDD-128
To:
Charlie Krueger - Resident Engineer
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
From: Mike Berg - Project Engineer
Date: May 8, 2006
cc:
Subject: Booster Pump Plumbing
Charlie,
Per your request please find attached quote from B&B Landscaping for furnishing and installing the
galvanized fittings and nipples at the booster pump.
B&B Landscaping F&I Galvanized Pipe
GCC Markup (10%)
TOTAL
$ 2,627.00
$ 262.70
$ 2,889.70
The lump sum amount requested for this extra work is $ 2,890.00