In response to your request, RBF Consulting is pleased to present this addendum to provide
additional design services for the improvements of Santa Teresa Boulevard. This scope of
work provides for separating Mantelli Drive from the current plan set into a separate bid
document and for providing for a traffic signal and intersection improvements at the
intersection of Santa Teresa Boulevard and Mantelli Drive. This scope of work further
provides for revising the existing Santa Teresa Boulevard "Ultimate" Improvement Plans to
show Mantelli Drive and the traffic signal at the intersection of Santa Teresa Boulevard as
existing improvements.
Enclosed for your review are the following exhibits: Scope of Services, Exhibit "A" and
Proposed Compensation, Exhibit "B ".
Should you have any questions, please do not hesitate to call me.
Sincerely,
IV/t,& /'ate lWilliam J. C s, P Senior Asso
H: \PDATA \35100063 \Proposal\Add4.wpd
cc: Accounting RBF
John Zellmer RBF
PLANNING DESIGN t CONSTRUCTION
1981 North Broadway, Suite 235, Walnut Creek, CA 94596 -3817 ■ 925.906.1460 ■ Fax 925.906.1465
Offices located throughout California, Arizona & Nevada ■ www.RBF.com
printed an recycled paper
RBF Consulting
Contract Agreement for JN 35- 100063.005
EXHIBIT "A"
SCOPE OF WORK
SANTA TERESA BOULEVARD WIDENING
AND MANTELLI DRIVE GAP CLOSURE PROJECT
ADDENDUM #4
SEPARATE BID PACKAGE FOR MANTELLI DRIVE
PHASE I ENGINEERING
TASK 1.0 GEOMETRIC APPROVAL DRAWINGS
March 5, 2001
Page 2 of 8
Consultant will prepare geometric approval drawings at the intersection of
Santa Teresa Boulevard and Mantelli Drive. The geometric approval drawings
will illustrate the transitions, striping and join conditions from the existing
condition at Santa Teresa Boulevard to the ultimate curb return location at the
intersection of Mantelli Drive. It is anticipated that no hardscape medians will
be developed on Santa Teresa Boulevard rather left turn pockets on Santa
Teresa Boulevard will be striped. The geometric approval drawings will, in
schematic format, illustrate the location of the traffic signal mast heads.
Consultant will gain Cities approval of the preliminary drawings before
commencing with final plans, specifications and estimates.
TASK 1.1 STREET IMPROVEMENT PLANS (Mantelli Drive Bid Set)
Consultant will assemble previously prepared street improvement and related
plans into new plan set for the construction of the Mantelli Drive project. They
include:
Plan
Intersection Detail
Plan and Profile (Mantelli)
Water Line Plan
Storm Drain Plan
Sound Wall Plan
Estimated Number of Sheets
1
1
1
1
1
TOTAL 5
RBF Consulting
Contract Agreement for JN 35- 100063.005
TASK 1.2
March 5, 2001
Page 3 of 8
Consultant will prepare new street improvement plans to accompany the
previously assembled plan sheets to complete a plan set. They include:
Plan
Estimated Number of Sheets
Title Sheet 1
Typical Section and Details 1
Plan and Profile (Santa Teresa Blvd.) 1
New Storm Drain Lateral 1
TOTAL 4
TRAFFIC IMPROVEMENT PLANS (MANTELLI DRIVE)
Consultant will assemble previously prepared traffic improvement plans into
new plan set for the construction of the Mantelli Drive project. They include:
Plan
Mantelli Drive Striping Plan
Street Light Plan
Estimated Number of Sheets
1
1
TOTAL 2
Consultant will prepare new traffic improvement plans to accompany the
previously assembled plan sheets to complete the plan set. They include:
Plan
Traffic Signal Modification Plan
Santa Teresa Blvd. Striping Plan
Estimated Number of Sheets
1
1
TOTAL 2
TASK 1.3 REVISE EXISTING SANTA TERESA BOULEVARD STREET IMPROVEMENT PLAN SET
Consultant will revise the previously prepared Santa Teresa Boulevard Street
Improvement Plan Set and other related plans to reflect the construction of
Mantelli Drive. The modifications to the existing plan set includes:
• Modifying the existing base topo to reflect Mantelli Drive and the
intersection of Santa Teresa Boulevard as constructed.
• Modifying the Santa Teresa Boulevard Plan and Profile Sheets to reflect
the construction of the intersection of Santa Teresa and Mantelli Drive.
• Modifying Storm Drain Plans to reflect construction of Mantelli Drive.
• Modifying Typical Sections Sheets deleting Mantelli Drive sections along
RBF Consulting March 5, 2001
Contract Agreement for JN 35- 100063.005 Page 4 of 8
with modifying other sheets referencing Mantelli Drive.
TASK 1.4 REVISE EXISTING SANTA TERESA BOULEVARD TRAFFIC IMPROVEMENT PLAN SET
Consultant will revise the previously prepared Santa Teresa Boulevard Traffic
Improvement Plan Set to reflect the construction of Mantelli Drive. The
modifications to the existing plan set includes:
Modifying the now existing Traffic Signal Plan to reflect the full street
improvements of Santa Teresa Boulevard
Modify Striping Plans, Traffic Control Plans and Street Light Plans to
reflect the construction of Mantelli Drive
TASK 1.5 TRAFFIC SIGNAL TIMING PLANS
As part of the RBF Project Team, Hartzog & Crabill Inc.(HCI), shall prepare
a Traffic Signal Timing Plan for the traffic signal at the following location:
- Santa Teresa Boulevard at Mantelli Drive (new traffic signal)
Three copies of the timing sheets for the project intersection will be provided
to the City.
Products: Timing Sheets for the Project Intersection
TASK 1.6 INTERSECTION TURNING MOVEMENT TRAFFIC COUNTS
In order to develop the signal timing, intersection turning movement traffic
counts will be taken for the morning, mid -day and afternoon peak hour at the
Mantelli intersection.
It is estimated that the City will provide twenty -four hour traffic counts to assist
in the development of the signal timing plans.
Product: 1. Morning, Mid -day and Afternoon Intersection Turning
Movement Traffic Counts (1 intersection)
Exclusions — Any work relating to the following items are specifically excluded
from the engineering services but may be added as additional services for an
additional fee:
RBF Consulting
Contract Agreement for JN 35- 100063.005
• Left Turn /Right Turn Storage Report
• Additional Traffic Engineering Reports
• Subconsultant Meeting Attendance
• Additional Peak Hour Traffic Counts
• Twenty -Four Hour Traffic Counts
• Additional Timing Sheets and Coordination Plans
TASK 1.7 DRY UTILITY NOTIFICATIONS
March 5, 2001
Page 5 of 8
Consultant will identify other utility owners within the sphere of the project
which may be affected by the proposed improvements. Consultant will provide
coordination interface to establish controls for utilities that would be included
within the right -of -way limits, identify agencies responsible for the design and
construction or relocation of said utilities and contact each agency to determine
what utilities relocation efforts are required by this project. This task excludes
preparation of dry utility relocation plans which will be prepared by others, if
required.
Utility potholing, if required, will be by City forces or the serving utility as
appropriate. Consultant will request information and notify utility at
appropriate milestones as necessary.
TASK 1.8 FINAL QUANTITY AND COST ESTIMATES
Consultant will prepare final quantity take off and cost estimates for each plan
submittal at 90% and 100 %. One composite quantity and cost estimate will be
provided. The final quantity take off will be utilized in the preparation of the
bid schedule.
TASK 1.9 SPECIFICATIONS
Consultant will prepare contract documents in accordance with the
requirements of the City of Gilroy. The City will provide its current
`boilerplate" contract forms, general conditions, and general provisions on a
diskette in Word format.
TASK 1.10 PROJECT MEETINGS
Consultant will attend up to one(1) coordination meetings with the City and
other agencies during the implementation of this phase of work.
RBF Consulting
Contract Agreement for JN 35- 100063.005
EXCLUSIONS
The following are excluded from this scope of work as part of this addendum:
March 5, 2001
Page 6 of S
1. Utility Relocation Plans other than water relocation plans.
2. Storm Water Pollution Prevention Plan /Notice of Intent.
3. Construction staking, inspection, administration, construction quantity calculations and
management.
4. Interconnect Plans
5. Traffic Control Plans
6. Construction Support Services
7. As -Built Drawings
8. Any item not specifically identified
RBF Consulting March 5, 2001
Contract Agreement for JN 35- 100063.005 Page 7 of 8
EXHIBIT "B"
"PAYMENT SCHEDULE"
SANTA TERESA BOULEVARD WIDENING
AND MANTELM DRIVE GAP CLOSURE PROJECT
ADDENDUM #04
The total payment to CONSULTANT for all work, service, material, equipment and
incidentals necessary for performing and completing the Tasks set forth in this agreement, shall
be for the sum of
CITY shall compensate CONSULTANT in proportion to the services performed and invoiced
to the CITY as outlined below, subject to Article 4 of this agreement.
SEPARATE BID PACKAGE FOR MANTELLI DRIVE
TASK
DESCRIPTION
FEE
Phase I
ENGINEERING
Task 1.0
Geometric Approval Drawings
$2,592.00
Task1.1
Street Improvement Plans (Mantelli Drive Bid Set)
$6,628.00
Task 1.2
Traffic Improvement Plans (Mantelli Drive Bid Set)
$5,808.00
Task 1.3
Revise Existing STB Street Improvement Plan Set
$4,008.00
Task 1.4
Revise Existing STB Traffic Improvement Plan Set
$5,508.00
Task 1.5
Traffic Signal Timing Plan
$1,610.00
Task 1.6
Intersection Turning Movement Counts
$698.00
Task 1.7
Dry Utility Notifications
$1,464.00
Task 1.8
Final Quantity and Cost Estimates
$1,704.00
Task 1.9
Specifications
$2,556.00
Task 1.10
Project Meetings
$1,072.00
Total Professional Fee
$33,648.00
RBF Consulting
Contract Agreement for JN 35- 100063.005
March 5, 2001
Page 8 of 8
Blueprinting, reproduction, messenger service and other direct expenses will be charged as
additional costs plus a fifteen percent (15 %) handling fee. A Subconsultant Management Fee
of fifteen percent (15 %) will be added to the direct cost of any subconsultant services to
provide for the costs of administration, subconsultant consultation and insurance. These
charges will be invoiced against previous authorizations.
The fees proposed herein shall apply until December 31, 2001. Due to ever - changing costs,
Consultant will increase those portions of the contract fee for which work must still be
completed after December 31, 2001, by ten - percent (10 %).
Santa Teresa Boulevard Widening Project
Addendum #4
Separate Bid Package For Mantelli Drive
Prepared For: City of Gilroy
Prepared By: RBF Consulting
Job No. 35- 100063.005
Date: January 11, 2001
Prepared By: William Conyers
Task No.
Task
Principal
Hours
Project
Manager
Hours
Project
Engineer
Hours
Design
Engineer
Hours
Cadd
Technician
Hours
Clerical
Hours
Survey
Crew Hours
Total
Hours
Fee Total
PHASE I
ENGINEERING
Task 1.0
Geometric Approval Drawings
2
6
0
20
0
0
0
28
$2,592.00
Task 1.1
Street Improvement Plans Mantelli Drive Bid Set
2
8
0
52
20
0
0
82
$6,628.00
Task 1.2
Traffic Improvement Plans Mantelli Drive Bid Set
01
8
32
0
24
01
0
64
$5,808.00
Task 1.3
Revise Existing Santa Teresa Blvd. Street Imp. Plan Set
0
4
0
32
16
0
0
52
$4,008.00
Task 1.4
Revise Existing Santa Teresa Blvd. Traffic Imp. Plan Set
0
10
32
0
16
0
0
58
$5,508.00
Task 1.5
Traffic Signal Timing Plans
0
0
0
20
0
2
0
22
$1,610.00
Task 1.6
Intersectioon Turning Movement Traffic Counts
0
0
0
8
2
0
0
$698.00
Task 1.7
Dry Utility Notification
0
12
0
0
0
0
0
12
$1,464.00
Task 1.8
Final Quantity and Cost Estimates
0
4
0
16
0
0
0
20
$1,704.00
Task 1.9
S ecifications
0
18
0
0
0
8
0
26
$2,556.00
Task 1.10
Project Meetings
2
6
0
0
0
0
0
8
$1,072.00
Subtotal Phase 1
6
76
64
148
76
12
0
372
$33,646.00
Hourly Rate
$170.00
$122.00
$100.00
$76.00
$68.00
$45.00
$178.00
Fee Total
$1,020.00
$9,272.00
$6,400.00
$11,248.00
$5,168.00
$540.00
$0.00
$33,648.00