HomeMy WebLinkAboutGraniterock/Pavex - Change Order No. 2I Citp of bilrop Public Works Department - Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0451; Fax (408) 846 -0429 CHANGE ORDER NO. CORRECTED To contract for: Gilroy Crossings Offsite Improvements City Project No.: Contractor: Graniterock/dba Pavex Construction Contract Date: 2 (7th St.) 11 -CDD -183 2/2212011 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Description of Work This change order is to cover the cost of additional quantities of sidewalk, curb &. gutter over the quantites in the original bid sheet. There was an additional 326. SF of curb & gutter, and an additional 335 SF of sidewalk, for a total increase of $21,896.00 All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work'), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and /or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. Change in working time granted by this change order ► All Extra Work authorized under this Change Order must be billed separately from the original contract. All bills for work done under this Change Order shall reference this Change Order. No. 2 (7th St.). I 0 Working Days Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost Percentage Initial $359,524.00 $28,969.44 6.06 %a $388,493.44 $21,896.00 $50,865.44 14.15% $410,389.44 I.(We) agree 3o make the above change subject to the terms of this Change Order for a NET INCREASE not to exceed $21 BBnite'Rack Company dba CPia�vex Construction Division APR �g g CONTRACT APR O 2 2 2 ®13 By: Date: RECOMMENDED BY: ACCEPTED BY: Graniterock- Pavex Divisien S Printed: Contract 1 Billing eet�_� Planted; 6727119 9:59:46AM Job No: 4162 Gilroy C+ :n ?g Off Site Imp Contract No PROJ 11 -COD -183 - Item Unit of CONTRACT To Date Bid Item or Number Description Measure Quantity Unit Price Total Quantity Total Task Cross -ref Quantity This Billing 001 PREPARE SWPPP LS 1.00 10,000,00. 10,000.00 0,06 0.00 001 002 TRAFFIC CONTROL IS 1.00 5,000.00- 5,000.00 0.00 9.00 002 003 ROADWAY EXCAVATION LS 1.00. 29,500.00 29,500.00 0 -00 0.00 003 004 CLEARING & GRUBBING LS 1.00 9,000,00 9,000.00 0.00 0.00 004 005 MOBILIZATION LS 1.00 6,000.00 6,000.00 0.00 0.00 005 006 IRRIGATION LS 1.00 24,859.00 24,859.00 0.00 0.00 006 007 CONSTRUCTION STAKING LS 1.00 3,390.00 :3,390.00 0.00 0.00 007 008 INSTALLINLET -TYPE GO EA 1.00 2,490.00 2,490.00 0.00 0.00 008 009 ADJUST INLET-TYPE GO EA 2.00 990.00 1,980.00 0.00 0.00 009 010 ADJUST UTILITY EA 9.00 549.00 4,941,00 0.00 0.00 010 O11 ROADSIDE SIGN - -ONE. POST EA 2.00 315.00 630.00 0.00 0.00 011 - 012 ROADSIGE:SIGN-- TWOPOSTS EA 1.00 385.00 385.00 0.00 0.00 012 013 RELOCATE ROADSIDE SIGN EA 1.00 995.00 195.00 0.00. 0.00 013 014 12 "CMP DOWN DRAIN LF 88.00 84.00 - 7,392.00 0,00 - 0.00 014 015 12 "X18 "CMP FITTING & TEE LS 1.00 340.00. 340.00 0.00 0,00 015 016 ROCK SLOPE PROTECT- METH0I13 B 1.00 4,000:00 4,000.00 0.00 0.00 016 017 ROCK SLOPE PROTECTION FARSI 1.00 50.00 50,00 0.00 9:00 017 018 CONSTRUCT CURB RAMP EA 4.00 2,700.00 10,800,00 0.00 0.00 018 019 MINOR CONCRETE -- SIDEWALKSF 5642.00 .5.00 28,210.00 0.00 0.00 019 020 MINOR CONCRETE-CURB TYPBA52 971.00 62:00 60;202.00 0.00 0.00 020 021 MINOR CONC -CURB TYPE A87 LF 28.00 119.00 3,332.00 .0.00 0.00 021 022 MINOR CONCRETE- CURB TYPHS 21.00 28,00 588.00 0.00 0.00 022 023 REMOVE TRAFFC STRIPE & MRLIS, 1,00 475.00 475,00 0.00 0.00 023 024 TRAFFIC STRIPE & MARKINGS LS 1.00 2,085.00 2,085.00 0.00 0.00 024 025 RETAINING WALL & -GUARD RAILS 1.00 33,000,00 33,000.OD 0.00 0.00 025 101 PREPARE SWPPP LS 1.00 5,000.00 5,000.00 1.00 5,000.00 101 102 TRAFFIC CONTROL LS 1.00 2,500.00 2,500.00 1,00 2,500.00 102 103 ROADWAY EXCAVATION LS 9.00 20,000.00 20,000.00 1100 20,000.00 103 104 CLEARING AND GRUBBING LS 9.00 10,000.00 10,000.00 1.00 10,000.00 104 105 MOBILIZATION - LS. 1.00 4,000.00 4,000.00 1.00 4,000.00 105 100. CONSTRUCTION STAKING LS 1.00 500.00 500.00 1,00 500.00 106 107 CONSTRUCT CURB RAMP- TYPE.K 9.00 2,500.00 22,500.00 7.00 17,500.00 107 108 CITY STANDARD CURB & GUTTER 430.00 61.00 26,230.00 756.00 46,116.00 108 109 MINOR CONCRETE -- SIDEWALKSF ,� /3325.00 6.00 19,950.00 3660.00 21,960,00 109 940001 DEMO SIDEWALK AND DAN TM /fl 1,00 1.00 1.00 0,00 0.00 940001 940002 TRAFFIC CONTROL /Mj r 1,00 1.00 1.00 0.00 0.00 940002 940003 AUTHORIZED OVERTIME 1.00. 1.00 1.00 0,00 0.00 940003 940004 ADJUST DI 1.00 1.00 9.00 0 -06 0.00 940004 Total Gross 359,528.00 127,576.00 Retention 12,757,60 Net Billed -7'1Jwa® ",i. - fy^ rA 114,818.40 : �+ .- CONFIDENTIAL PROPERTY OF GRANITEROCK "" � L f � � }} b:::= Cftp of Ofrrop Public Works Department 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0450; Fax (408)846 -0429 CHANGE ORDER INFORMATION SHEET ❑ This change order is for work on a project that is currently still in construction. A copy of a valid, current insurance certificate has been attached. The work on this project, including the work on this change order, has been completed. The change order work was completed by the contractor based on a field order. The contractor is completely finished and will not return to the worksite, unless there is a warranty issue during the warranty period. Attachments: ❑ Copy of valid, current insurance certificate(s) 2 copies of Change Order Form By: Date: Z 3 Comments: With the completion of this change order, the contract retention can be paid and the project can be closed out completely. The Notice of Completion has already been to Council, and more than the required 35 days has passed since recordation. All HUD documentation requirements have been met.