CHANGE ORDER NO. 23
To contract for :
Christmas Hill Park Improvements
Project 1'03-CDD-lOO
Contractor:
Penna-Green Hydroseeding
Contract Date:
7/17/2002
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Uvas Phase II - Trail
1 Install 15 inch RCP
2 Provide and Install Manhole
3 Extra Staking
4 Demo 36 inch CMP
5 Install 36 inch RCP
6 Raise Manhole
7 Retaining wall Extra Concrete
38 LF
1 ea
1 ea
11 LF
47 LF
1 ea
1 ea
$115.001 LF
$12,220.001 ea
$650.00 1 ea
$89.33 1 LF
$300.00 1 LF
$1,600.001 LF
$3,894.00 1 LF
$4,370.00
$12,220.00
$650.00
$982.67
$14,100.00
$1,600.00
$3,894.00
$37,816.67
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
I ~e) agree to make the above change
subject to the tenus of this Change Order
for the NET INCREASE of $37,816.67
By:
ACCEPlED BY:
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percentage
$1,556,117.00
$799,916.80 51.0%
$2,356,033.80
$37,816.67
$837,733.47 54,0% *1311-
$2,393,850.47
*Requires emergency authorization if greater than 25%.