HomeMy WebLinkAboutDon Chapin Co. - 2014 Agreement - Project No. 15-PW-216 - Change Order No. 2Citp of Oifrop
Public Works Department - Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0451; Fax (408) 846 -0429
CHANGE ORDER NO. 2
To contract for: 6th Street Improvements, LED Trail and Led Upgrad City Project No.: 15 -PW -216
Contractor: Don Chapin Company Contract Date: Oct. 22, 2014
This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and
Description of Work
Full and complete reimbursement for all costs (incl. taxes, bonds, and insurance) for the following extra work:
Due to unforeseen conditions, 6,100 square of roadway was reconstructed to address sub -base failures underneathe the
roadway. This work resulted in 120 lineal feet of roadway north of the Eigleberry Street & 6th Street intersection to be
reconstructed.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained
herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses
associated with this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit,
delay, disruption, loss of efficiency and any and all other direct and /or indirect costs or expenses associated with the Extra
Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of
the Contract associated with the Extra Work.
Change in working time granted by this change order:
► All Extra Work authorized under this Change Order
must be billed separately from the original contract. All
bills for work done under this Change Order shall
reference this Change Order No. 2.
I (We) agree to make the above change subject to the
terms of this Change Order for a NET INCREASE not
to exceed $76,860.00.
CONTRACTOR
RECOMMENDED BY:
ACCEPTED BY:
20 Working Days
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to DE
Revised Contract Price
Cost Percentage
$805,729.00
$44,720.00 5.55% of bid
$850,449.00
$76,860.00
tE $121,580.00 15.09% of bid
$927,309.00
Date: —1 '�� 1�
Date
er Dalp
ate
Date