Loading...
HomeMy WebLinkAboutRolfe Construction - 2014 Agreement - Change Order No. 08Up of OfCrop Public Works Department - Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0451; Fax (408) 846 -0429 CHANGE ORDER NO. 8 To contract for: Gilroy- Morgan Hill Joint Trunk Sewer Main City Project No.: 14 -PW -208 Contractor: Rolfe Construction, Inc. Contract Date: August, 2014 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Extra Work at Agreed Upon Lump Sum Compenstation Price: This CCO is warranted due to additonal work caused by delay to the critical path schedule and ongoing work in regards to the controlling operation of work. (The impact to the controlling operation which caused the delay, and ultiamtely temporary suspension between March through May 2015). This CCO therefor provides for additional work related the construction of a tempiorary 24" sewer bypass that was not provided for on the contract documents due to conflcit with the existing pipeline and bore pit / auger machine inclsuive of labor and provision of a temporary bypass system at Hwy 152 crossing due to alignment conflict within the jacking pit. This additional item of work was necessary per the Project Manager and Resident Engineer's in effort to remove and replace the sewer force main crossing at Hwy 152. (See attached Rolfe DEWRs, RFI No. 8 and total cost estimate for all additional costing information). All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. Change in working time granted by this change order: ► All Extra Work authorized under this Change Order must be billed separately from the original contract. All bills for work done under this Change Order shall reference this Change Order No. 8. I (We) agree to make the above change subject to !biiie terms of this Change Order r a N C t to exceed $22,641.00. CONTRACTOR By: Rolfe Construction, Inc. RECOMMENDED BY: ACCEPTED BY: 2 Working Days Cost Percentage Initial Contingency Amount 815,095.00 91% used Original Contract Price $3,423,467.00 Previous Change Orders $715,249.82 20.89% of bid Total to Date $4,138,716.82 This Change Order $22,641.00 Total Change Orders to Date $737,890.82 21.55% of bid Revised Contract Price $4,161,357.82 Date: 3/16/2016 (rev) Date "Project En&erer /Project Manager Date AfiJ4"4-1_ 61171146 J�Vr City Engineer Date M _ r-1 A A _/' _ % _ City Administrator Date