HomeMy WebLinkAboutRolfe Construction - 2014 Agreement - Change Order No. 09Citp of (bitrop Public Works Department - Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0451; Fax (408) 846 -0429 CHANGE ORDER NO. 9 To contract for: Gilroy- Morgan Hill Joint Trunk Sewer Main City Project No.: 14 -PW -208 Contractor: Rolfe Construction, Inc. Contract Date: August, 2014 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Extra Work at Agreed Upon Lump Sum Compenstation Price due to critical path delays in construction of the new 42" main between the temporary suspension period and required (revised workplan) extra work required to cross the Princevalle Storm Drain (ditch) per SCVWD permitting. This CCO required additional Jack and Bore pit excavation and larger auger machine which was due to found p.c.c. encasement of the exist 24" main to be hand removed not oringianlly planned by the Engineer. This CCO therefor is for the provision of extending the rental and site safety period for manhole and jack / bore pit safety plating, shoring, portable restroom extension, water permitting, temporary safety fencing, stockpile /yard use extension durning the agreed upon project suspension period of 3/17/15 to 6/5/15. (See attached vetted and reviewed Rolfe receipts and costs for additional costing information). All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and /or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. Change in working time granted by this change order: ► All Extra Work authorized under this Change Order must be billed separately from the original contract. All bills for work done under this Change Order shall reference this Change Order No. 9. I (We) agree to make the above change subject to the terms of this Change Order NET INCREASE not to exceed $491 7.29 CONTRACTOR 0 Working Days I Cost Percentage Initial Contingency Amount 815,095.00 97% used Original Contract Price $3,423,467.00 Previous Change Orders $737,890.92 21.55% of bid Total to Date $4,161,357.92 This Change Order $49,837.29 Total Change Orders to Date $787,728.21 23.01% of bid Revised Contract Price $4,211,195.21 By: Rolfe Construction, Inc. Date: 3/1-111(- RECOMMENDED BY: IVIIAI 3/16/2016 (rev) Co ruction Manag Date ACCEPTED BY: - S lt7 Id / G roeectt Eng er /Project Manager Date 9UAaAJ j f City Engineer Date City Administrator Date