CONTINGENCY CHANGE ORDER NO. 5
To contract for: Eigleberry Street Resurfacing Projc..t • •City Project No.: 14 -PW- 213 /STPL- 5034(025)
Contractor: Graniterock Inc. Contract 3/1/2015
This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and
Contractor. All copies forwarded to Contractor for signature shall be returned to the City of Gilroy properly filled out. Upon
acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work.
Description of Work
Significant change order work was added to this project. In order to provide working days to perform the change order work,
additional working days are being added to the project via this change order as follows: 31 working days for construction of
additional and redesigned access ramps, 1 working days for removal of tree roots, 5 working days to construct concrete
cross - gutter @ 9th Street, 4 working days to perform digouts and set grades, and 6 working days to perform the intersection
work in bid alternate A for a total of 47 additional working days.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with
this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption,
loss of efficiency and any and all other direct a.-)d /or indirect costs or expenses associated with the Extra Work and hereby
waives any right to claim any further cost and time impacts at any time during and after completion of the Contract
associated with the Extra Work.
Change in working time granted by this change order:
► All Extra Work authorized under this Change Order
must be billed separately from the original contract. All
bills for work done under this Change Order shall
reference this Change Order No. 5.
I (We) agree to make the above change subject to the
terms of this C nge Order with NO CHANGE IN
PRICE��1n �f1
Cii�ip
By: ovitch, Area Manager
- -,
RECOMMENDED BY:
ACCEPTED BY:
on
47 Working Days
Cost
Percentage
Contingency Amount
$906,403.00
123.0% used
Original Contract Price
$1,189,355.00
Previous Change Orders
$1,114,499.20
93.71% of bid
Total to Date
$2,303,854.20
This Change Order
$0.00
Total Change Orders to Date
$1,114,499.20
93.71% of bid
Revised Contract Price
$2,303,854.20
Date:
OCT 2 0 2016