HomeMy WebLinkAboutGranite Rock - West Branch Llagas Creek Trail - Change Order No. 1City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0450; Fax (408) 846-0429 CHANGE ORDER NO. 001 To contract for: West Branch Llagas Creek Trail Contractor: Graniterock Company Contract Date: January 30, 2018 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work This change order provides for the following: Compensation for any and all direct and indirect costs associated with Notice of Potential Claim 01 (NOPC 01), less escalation costs that will occur in the 2019 season that were estimated and presented at the 03.18.19. NOPC 01 addresses costs incurred by the Contractor as a result of delays to critical path activities due to permitting issues with the California Department of Fish and Wildlife 1600 Lake and Streambed Alteration Agreement. Escalation costs for materials, equipment, and labor as cormnunicated at the 03.18.19 project meeting and as specifically identified in the Record of Negotiation will be reimbursed to the Contractor as an adjustment to the contract unit prices for selected items with a balancing change order at completion of contract. Method of Payment for CCO 001 is to be Lump Sum. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall be reset to 95 working days. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. Cost Percentage Initial Graniterock Company hereby a ee to Original Contract Price $1,814,859.42 mak a ab a changes Previous Change Orders $0.00 0.00% 5-T su ect to the to s of this FgeOr r Total to Date $1,814,859.42 fo t e NET REAS of $1 This Change Order $164,009.71 Total Change Orders to Dal $164,009.71 9.04% Sf Revised Contract Price $1,978,869.13 i 1 h-` � 1r7N.r-S A-r1 PRINT NAME IAND T TLE Date: RECOMMENDED BY: Cons do JY�a Date ACCEPTED BY: City Administrator Date enginee Date Project Engineer Date I oea Minn �, o.nm.�mw>wn�.- 3 "gyp O » 3 w F n s V. 8 e r v$ v$ R D w Z 3 rx to Ln 00 a"��nm Intl j j a a '� W -s n o 9 � � D � U � f O � A i 3 K ^ a I o a Boa R=a c�N 13 m m ^ 03 Z a D O E z m - '_ f1 = (1 m f1 O .D a In m Z — — — ad ------ n �p z m :i G1 W s S > O Im r- --II in^ F ^ w U Oho Y N N i A N A P Wf a A '� o p ~ O.N W A g W J V b a Z f�t a wpmv rwxTNN� o w 3 � g — o i o a m a g x is c P v to Om— W A — T » 3 R Q 3 `v o o d $ OO � H i � gotig Wp N N C mb">$: F+ ,- Q0 ih in VF V V V t r r r A Ol W A Ol N lO In F~+ p p tO V O V'1 V Ol 00 T O O O O 0o O O 0 0 0 0 In 0 0 VT i^ Vf to to VF i, r r r to OD W V1 V N �I O A A W 0 W O N W v Pi 00 A to J O O O O O O O O 0 O O V t i in U, to in F+ J 0) W 01 A r 00 V FA+ W Ln W N 0000 to r O O N 0 0 0 0 0 0 to 0 0 W nnnx�-{-{- < < < 7o Z 2 Z j V} y Vf i/ VF V tl 1 O J N N r r w v lW0 O Ot t0)l1 N A N 0 0 0 0 �o Vf in Vl N VF i, VT A s r r r r A N Ul O V J W O V 0o O L� L. w m V LO V 0 0 0 0 to to th to iti to Ur -y In In 9) O VAi w l!t O O O O_ m in t/F VF {n iJf in V4 ��